Almost everything that goes wrong on an underfloor installation goes wrong before the screed arrives, and almost none of it can be put right afterwards. That gives the installation sequence a weight it does not carry on a radiator job, where a mistake is a morning's work to undo.
This article covers Module 6 of the PlumbMate underfloor heating course: the installation sequence, working with the other trades, siting the manifold, insulation and edge strip, laying and fixing the tube, plated and foil floors, and the pressure test that has to happen before the pour. There is a 10-question mock test at the end.
The sequence
Seven steps, in this order:
- First fix the main wiring
- First fix domestic services below the insulation
- Lay the floor insulation
- Fix the manifolds in position
- Install the underfloor tube
- First fix the primary flow and return
- First fix the remaining hot and cold
Two of those positions surprise people, and both cost money when they are wrong.
The first is that wiring goes in first. Before that step is complete, the boiler, cylinder, thermostat and wiring centre positions all have to be agreed — because a thermostat position agreed after the plaster is on is a chase in a finished wall.
The second is that the manifold is fixed before the tube is laid. Laying pipe towards a position nobody has committed to is how tails end up three metres short, and within the floor there is no joint available to make up the difference.
Before any of it starts, the design has to state the coil numbers and lengths, the pipe spacings and the flow rates per zone. Storage matters too: keep tube dry, out of sunlight, away from sharp objects and chemicals, and avoid soldering anywhere near it. If the site might freeze before commissioning, add antifreeze — and flush thoroughly afterwards.
The other trades
Underfloor touches more trades than any other part of a plumbing installation, and each of them needs something specific from you:
- The electrician needs the thermostat positions at first fix.
- The joiner needs to know about notching and blocking — before the joists are cut, not after.
- The screeder needs to know the pipe is down there and that it is pressurised.
The rule that covers the rest: trades involved are briefed; trades not involved are notified and excluded. A floor full of pipework with nobody watching it is an expensive thing to leave unattended.
Two points on documentation. Below the law, the manufacturer's instructions take precedence over a standard, so follow the instructions. Where instructions conflict with statute, statute wins. And read the installation instructions first, not last — underfloor systems differ far more between manufacturers than radiator systems do, and assuming the last one you fitted tells you how this one works is a reliable way to get it wrong.
Siting the manifold
The manifold goes strategically, and as centrally as possible, in the area it serves.
Two reasons, and both are worth being able to say out loud:
- Shorter pipe tails. Every metre of tail is coil you paid for that heats nothing.
- Less uncontrolled energy. Tails crossing heated areas on their way somewhere else give up heat that no room thermostat governs.
Height has nothing to do with it, and neither does the heat source: two insulated primaries travel further than a dozen tails.
It also has to stay accessible. Meters get read, lockshields get set, actuators get replaced. A manifold boxed into a cupboard behind a fitted wardrobe is a manifold nobody will service. And label every port as you connect it, while you still know which room is which — not from memory a fortnight later.
Insulation, edge strip and conduit
Part L sets a U-value, not a board thickness: in England a new floor must reach 0.18 W/m²K or better under Approved Document L 2021, and the U-value calculation decides how deep the insulation goes. Under the pipe, BS EN 1264-4 asks for at least 1.25 m²K/W on a ground floor and 0.75 over a heated room. Protect it from the wet screed with polythene: at least 0.15 mm thick and lapped 80 mm (BS EN 1264-4), taped liquid-tight under a calcium sulphate screed.
The edge strip goes round every perimeter, every column and every threshold, and it rises from the base up past the finished floor surface — not just the top of the screed — and is trimmed only once the floor covering is down. It is doing two jobs: an insulation barrier at the perimeter, and an expansion gap for a slab that will grow when it is heated.
Wherever the pipe crosses a screed joint or a threshold, sleeve it in a larger conduit for 400 mm either side, and fix the conduit so it cannot migrate along the pipe while the screed is being placed.
And keep the first pipe run 100 mm off the wall, the usual practice. BS EN 1264-4’s own minimum is more than 50 mm from a wall, and 200 mm from a chimney, flue or open fireplace.
Laying and fixing the tube
Any of the standard fixing methods is acceptable: clips pushed into the insulation, clip rails, matrix overlays, or fixing to reinforcement mesh. Choose for the floor you have rather than for habit.
Handling the pipe is where craftsmanship shows:
- Pull the pipe to shape, never force it. The print line down the side of the tube tells you whether it has twisted — if the line spirals, the pipe is under torsion and it will fight you at every bend.
- Cut square, with a plastic pipe cutter, and leave no burrs.
- No joints within the floor. If a repair joint becomes unavoidable, it must be located and recorded on a record drawing in the building log book — because somebody will need to find it one day.
Expansion is worth a number: above ground, roughly 10 mm per linear metre from cold to 60 °C for PE-X or polybutylene; multilayer pipe moves far less. Once the pipe is embedded in screed that movement is prevented, so you allow for it in the tails and at the manifold, not in the floor.
Plated and foil floors
Many makers’ heat emission plates are scored to break at set points: a third from one end and a sixth from the other. Break them groove uppermost over a straight edge, then clean off the burrs. For any other length, score deeply with a knife and cut with a hacksaw across the plate.
On both plated and foil systems the pipe runs parallel to the joists, and there is a minimum of 100 mm of mineral wool between the joists beneath — for downward heat loss and for airborne sound.
Pressure test, then screed
The pressure test happens before the screed, and the pipe stays pressurised throughout the pour.
That is not belt and braces. It is the only arrangement in which damage announces itself at the moment it happens — on the gauge, while the screed is still workable and the pipe is still reachable. Test afterwards and a barrow wheel through a pipe becomes a floor you take up.
Before the screed arrives: board out the walking and barrow routes, and check the edge strip and the conduits one last time. Screed at 65 to 75 mm in total, with at least 30 mm over the pipe (BS EN 1264-4), reinforced if the specification calls for it.
Then 21 days for sand and cement (7 for calcium sulphate). And never use the heating to cure it.
📝 10-Question Mock Test
Click an option to see whether you got it right. Explanations appear instantly — no submitting at the end.
Wiring first, with the boiler, cylinder, thermostat and wiring centre positions all agreed. A thermostat position settled after the plaster is on means chasing a finished wall.
Laying pipe towards a position nobody has committed to is how tails end up short — and within the floor there is no joint available to make up the difference.
Follow the instructions. Where instructions conflict with statute, statute wins. And read them first — underfloor systems differ far more between makers than radiator systems do.
Two reasons: shorter tails, and less uncontrolled heat from pipes crossing heated rooms on their way elsewhere. It also has to stay accessible for reading meters, setting lockshields and replacing actuators.
It rises from the base up past the finished floor surface and is trimmed only once the floor covering is down. It is doing two jobs — insulation barrier and expansion gap — and it goes round every perimeter, column and threshold.
400 mm either side, with the conduit fixed so it cannot migrate along the pipe while the screed is being placed. The two slabs will move relative to each other.
If the line spirals, the pipe is under torsion and will fight you at every bend. Pull the pipe to shape — never force it.
Pipe within the floor is laid without joints as a rule. Where one cannot be avoided, somebody will need to find it one day, and the record drawing is how.
A burr left in the pipe groove will damage the pipe. Plates are broken groove uppermost over a straight edge, or scored deeply and hacksawed for other lengths, then deburred.
The circuits stay under pressure through the pour so that damage shows at once. A falling gauge means a pipe has been hit: stop the pour while the screed is still workable and the pipe still reachable.
The theme running through all of it is that underfloor work is irreversible in a way most plumbing is not. Almost every item in this module — the sequence, the manifold position, the edge strip, the conduit, the record drawing, the pressure test held through the pour — exists because there is no second chance once the screed truck has left.