Almost everything that goes wrong on an underfloor installation goes wrong before the screed arrives, and almost none of it can be put right afterwards. That gives the installation sequence a weight it does not carry on a radiator job, where a mistake is a morning's work to undo.

This article covers Module 6 of the PlumbMate underfloor heating course: the installation sequence, working with the other trades, siting the manifold, insulation and edge strip, laying and fixing the tube, plated and foil floors, and the pressure test that has to happen before the pour. There is a 10-question mock test at the end.

The sequence

Seven small pictures of the same corner of a hall at each stage: cables and back boxes on the wall; a water pipe and a duct on the bare slab; insulation and edge strip down; the manifold bracketed on the wall; pipe stapled down and running to the manifold; the primary flow and return run to the manifold; the other hot and cold pipework. Steps 1 and 4, the wiring first and the manifold before the pipe, are outlined as the ones that surprise people.
Seven steps in this order. Wiring first, and the manifold before the pipe, are the two that surprise people.

Seven steps, in this order:

  1. First fix the main wiring
  2. First fix domestic services below the insulation
  3. Lay the floor insulation
  4. Fix the manifolds in position
  5. Install the underfloor tube
  6. First fix the primary flow and return
  7. First fix the remaining hot and cold

Two of those positions surprise people, and both cost money when they are wrong.

The first is that wiring goes in first. Before that step is complete, the boiler, cylinder, thermostat and wiring centre positions all have to be agreed — because a thermostat position agreed after the plaster is on is a chase in a finished wall.

The second is that the manifold is fixed before the tube is laid. Laying pipe towards a position nobody has committed to is how tails end up three metres short, and within the floor there is no joint available to make up the difference.

Before any of it starts, the design has to state the coil numbers and lengths, the pipe spacings and the flow rates per zone. Storage matters too: keep tube dry, out of sunlight, away from sharp objects and chemicals, and avoid soldering anywhere near it. If the site might freeze before commissioning, add antifreeze — and flush thoroughly afterwards.

The other trades

Underfloor touches more trades than any other part of a plumbing installation, and each of them needs something specific from you:

The rule that covers the rest: trades involved are briefed; trades not involved are notified and excluded. A floor full of pipework with nobody watching it is an expensive thing to leave unattended.

Two points on documentation. Below the law, the manufacturer's instructions take precedence over a standard, so follow the instructions. Where instructions conflict with statute, statute wins. And read the installation instructions first, not last — underfloor systems differ far more between manufacturers than radiator systems do, and assuming the last one you fitted tells you how this one works is a reliable way to get it wrong.

Siting the manifold

The manifold goes strategically, and as centrally as possible, in the area it serves.

Two reasons, and both are worth being able to say out loud:

  1. Shorter pipe tails. Every metre of tail is coil you paid for that heats nothing.
  2. Less uncontrolled energy. Tails crossing heated areas on their way somewhere else give up heat that no room thermostat governs.

Height has nothing to do with it, and neither does the heat source: two insulated primaries travel further than a dozen tails.

It also has to stay accessible. Meters get read, lockshields get set, actuators get replaced. A manifold boxed into a cupboard behind a fitted wardrobe is a manifold nobody will service. And label every port as you connect it, while you still know which room is which — not from memory a fortnight later.

Insulation, edge strip and conduit

Part L sets a U-value, not a board thickness: in England a new floor must reach 0.18 W/m²K or better under Approved Document L 2021, and the U-value calculation decides how deep the insulation goes. Under the pipe, BS EN 1264-4 asks for at least 1.25 m²K/W on a ground floor and 0.75 over a heated room. Protect it from the wet screed with polythene: at least 0.15 mm thick and lapped 80 mm (BS EN 1264-4), taped liquid-tight under a calcium sulphate screed.

The edge strip goes round every perimeter, every column and every threshold, and it rises from the base up past the finished floor surface — not just the top of the screed — and is trimmed only once the floor covering is down. It is doing two jobs: an insulation barrier at the perimeter, and an expansion gap for a slab that will grow when it is heated.

Wherever the pipe crosses a screed joint or a threshold, sleeve it in a larger conduit for 400 mm either side, and fix the conduit so it cannot migrate along the pipe while the screed is being placed.

And keep the first pipe run 100 mm off the wall, the usual practice. BS EN 1264-4’s own minimum is more than 50 mm from a wall, and 200 mm from a chimney, flue or open fireplace.

Laying and fixing the tube

Any of the standard fixing methods is acceptable: clips pushed into the insulation, clip rails, matrix overlays, or fixing to reinforcement mesh. Choose for the floor you have rather than for habit.

Handling the pipe is where craftsmanship shows:

Expansion is worth a number: above ground, roughly 10 mm per linear metre from cold to 60 °C for PE-X or polybutylene; multilayer pipe moves far less. Once the pipe is embedded in screed that movement is prevented, so you allow for it in the tails and at the manifold, not in the floor.

Plated and foil floors

Many makers’ heat emission plates are scored to break at set points: a third from one end and a sixth from the other. Break them groove uppermost over a straight edge, then clean off the burrs. For any other length, score deeply with a knife and cut with a hacksaw across the plate.

On both plated and foil systems the pipe runs parallel to the joists, and there is a minimum of 100 mm of mineral wool between the joists beneath — for downward heat loss and for airborne sound.

Pressure test, then screed

A room of the course house halfway through the screed: semi-dry screed laid and ruled off over pipe stapled to the insulation, scaffold boards across the bare pipe as a barrow run with a loaded barrow on them, and the manifold on the wall with a test gauge, its needle in the green band between 4 and 6 bar. An inset shows the needle dropping: stop, and find it while the screed is still workable.
The test stays on through the pour: a barrow wheel through a pipe shows on the gauge at once.

The pressure test happens before the screed, and the pipe stays pressurised throughout the pour.

That is not belt and braces. It is the only arrangement in which damage announces itself at the moment it happens — on the gauge, while the screed is still workable and the pipe is still reachable. Test afterwards and a barrow wheel through a pipe becomes a floor you take up.

Before the screed arrives: board out the walking and barrow routes, and check the edge strip and the conduits one last time. Screed at 65 to 75 mm in total, with at least 30 mm over the pipe (BS EN 1264-4), reinforced if the specification calls for it.

Then 21 days for sand and cement (7 for calcium sulphate). And never use the heating to cure it.

📝 10-Question Mock Test

Click an option to see whether you got it right. Explanations appear instantly — no submitting at the end.

Your score: 0 / 10
Question 1 of 10
Who is first on site at the start of an underfloor installation, and why?
Question 2 of 10
When is the manifold fixed in position?
Question 3 of 10
The manufacturer's instructions are more demanding than the relevant standard. What do you follow?
Question 4 of 10
A builder wants the manifold in the garage by the boiler, out of the way. What do you tell him?
Question 5 of 10
How far up does the edge strip extend?
Question 6 of 10
Two screed bays meet at a doorway, and a circuit crosses between them. How far each side of the joint does its conduit sleeve run?
Question 7 of 10
What does the print line down the side of the tube tell you?
Question 8 of 10
A repair joint in a buried circuit becomes unavoidable. What must happen?
Question 9 of 10
Why must the burrs be cleaned off a cut plate before the pipe goes in?
Question 10 of 10
Halfway through the screed pour, the gauge on the manifold starts to fall. What does it tell you?

The theme running through all of it is that underfloor work is irreversible in a way most plumbing is not. Almost every item in this module — the sequence, the manifold position, the edge strip, the conduit, the record drawing, the pressure test held through the pour — exists because there is no second chance once the screed truck has left.