The survey is where a heat pump job is won or lost. Every problem found here costs a phone call; the same problem found on installation day costs a return visit, and some of them cannot be corrected at all once the system is in. This is the module that decides whether the design in Module 2 can actually be built on this property.

This covers Module 4 of the PlumbMate heat pumps course: the pre-installation checklist, selecting the unit from manufacturer's data, sizing a ground array, siting and noise, the electrical supply and structure, and assessing an existing system. There is a 10-question mock test at the end.

The pre-installation checklist

The checklist forces every prerequisite to be checked and recorded before work begins. It is not a formality — it produces a genuine decision, proceed or not, recorded with reasons. The headings group into four questions:

One failure stops the job

If a single item fails, the installation cannot proceed as specified. Record the failure with its reasons and the calculation behind it, revise the design — a larger buffer, a different collector arrangement, a supply upgrade — then re-check the item.

Proceeding and fixing it afterwards is not an option. Some failures cannot be corrected once the installation is complete, and noting a known defect in the handover pack is not a resolution.

Record, revise, re-check, then proceed.

Selecting the unit from manufacturer's data

Manufacturers publish output at several sets of conditions, and the figures differ substantially between them. Selecting from the wrong row quietly undersizes the installation.

Read the condition notation first

A unit quoted at 8.9 kW at B0/W35 might give only 8.6 kW at B0/W45, because a greater lift means less output and a lower COP. Find the row matching your design flow temperature before comparing anything.

Closest fit above the load

Suppose the design peak heat loss is 8 kW at a design flow temperature of 45 °C, and three units offer 6.2 kW, 8.4 kW and 10.5 kW at that condition. The 8.4 kW unit is correct: it is the smallest that meets the load.

What the data supplies, and what it does not

Manufacturer's documentation gives everything specific to the machine: outputs at stated conditions, electrical characteristics and starting current, sound power level, required clearances, minimum system volume, permitted starts per hour, and nominal flow rate.

It knows nothing about the property. The design external temperature comes from published regional climate data, and the room-by-room heat losses come from your own survey and calculation. Keep the two sources clear in your head — exam questions test exactly that boundary.

Sizing a ground array

The four ground collector arrangements
Depths and spacings are the ones that get asked.

A ground array is sized in three steps, plus a fourth that is easy to forget.

Step one: deduct the compressor

The ground does not supply the whole output. The compressor's electrical input becomes heat in the system too, so only the difference has to come from the ground.

ground extraction = output − electrical input

A 9 kW unit at a COP of 4 draws 9 ÷ 4 = 2.25 kW, so extraction is 9 − 2.25 = 6.75 kW. Sizing on the full 9 kW would make the array a third larger than necessary — several hundred metres of unnecessary trenching.

Step two: divide by the yield

collector length = extraction (W) ÷ extraction rate (W/m)

At 20 W/m: 6750 ÷ 20 = 338 m of pipe.

The extraction rate depends on two things. Ground conditions — wet, dense soils conduct well and support high rates; dry sandy ground supports far less. And the annual run hours, expressed as FLEQ (full load equivalent hours): a system running 2400 FLEQ hours draws far more from the ground over a season than one running 1200, so the permissible rate per metre is lower and the array must be longer.

For a rough sense of scale, a horizontal array yields somewhere around 10–40 W per m² of ground, and a vertical borehole around 20–55 W per metre of borehole. Use those as a sanity check, not as design figures — the number you size on comes from the array designer or the software.

Step three: split it into loops

That 338 m is the total pipe, not one continuous run. Push it all through a single circuit and the pressure drop defeats the circulator, so the array is divided into several equal loops brought back to a manifold. Equal is the important word: identical lengths take a fair share of the flow on their own, whereas unequal ones need balancing you can no longer reach once the trench is backfilled.

As a working guide, a loop runs to about 100 m in 25 mm pipe, rising to about 400 m in 40 mm. In 25 mm, 338 m becomes four circuits of roughly 85 m.

Step four: check it fits

At 1 metre centres, each metre of pipe occupies a metre-wide strip one metre long — so the area in square metres equals the pipe length in metres. 340 m of pipe needs 340 m². Compare that against the genuinely usable area, remembering the array must clear buildings, drains, trees and boundaries.

If it does not fit, the check fails and the design must change: vertical boreholes instead of horizontal, or a reduced load through fabric improvement. If the answer is boreholes, the shape of the job changes — typically 100–150 mm diameter, drilled between 15 and 200 m, grouted, and spaced at least 5 m apart. Any closer and neighbouring boreholes draw on the same rock.

Where there is open water on the plot, a pond or lake loop is worth assessing: reckon on at least 3 m of depth and roughly 9 m² of water surface per kW.

Two ways undersizing bites

There is no tolerance to apply here. An undersized array progressively depletes the ground, so performance degrades over seasons rather than failing immediately — which makes it a particularly unpleasant fault to inherit. Nor can you recover a shortfall by tightening the centres: adjacent pipes then draw on the same ground and the rate per metre falls.

The faster failure is frost heave. Draw heat out faster than the ground can replace it and the soil around the pipe freezes, expands and lifts — taking the pipe, and whatever is laid over it, with it. That is why depth is specified as well as length: practice puts a trench at around 1.2 m, CIBSE gives a range of 0.8–2.0 m and prefers at least 1.5 m where the ground allows, and the local frost line is the floor rather than the target.

Siting and noise

Three factors, none of them aesthetic

Structure-borne noise is the one that generates complaints

Noise travelling through the building fabric is far more troublesome than airborne noise, and it is the usual cause of complaints from inside the dwelling. Two measures break the path:

A lightweight timber-framed wall acts as a sounding board and is among the worst mounting positions available.

Siting a ground source unit indoors

Ground source units usually go in a garage, utility room or outbuilding. Check five things: the unit's dimensions, its weight against the floor, the manufacturer's clearances, whether compressor noise will transmit into living space, and whether it can be reached for service. A habitable room is generally the worst choice.

Electrical supply, structure and access

The electrical input service

Establish on the survey whether the supply can carry the additional load, including starting current — which matters as much as running current, particularly on a fixed-speed unit. Check whether the supply is single or three phase, the main fuse rating, and whether the consumer unit has capacity for a dedicated circuit. The installation must also have proper means of isolation with a correctly rated protective device.

Settle the DNO position here too, not the week before installation. A connection needing prior approval or network reinforcement can take weeks.

Structural suitability

Three loads to think about. A filled cylinder is a substantial point load, and one on an upper floor is the case most often overlooked. A wall-mounted unit imposes load on the wall. And forming openings for pipework can affect structural elements — core drilling through a lintel is a real risk on these jobs.

Access, in three dimensions

Assessing the existing system

On a retrofit, five checks decide how much of the existing installation survives — and the last one is not optional.

Emitters

The decisive question is whether each existing emitter can deliver its own room's heat loss at the design flow temperature. That means applying the manufacturer's correction factor room by room, not judging the system as a whole. This is the check that catches the retrofit where nobody upsized the radiators.

Pipework

A boiler system designed around a 20 K temperature difference carries roughly a quarter of the flow a heat pump system at 5 K needs for the same load. Undersized pipework produces excessive velocity, noise and pressure drop, and may make the design flow rate unachievable. Check the index circuit in particular. Material matters less than size: copper is fine, and plastic must be oxygen-barrier pipe.

Condition

Years of magnetite sludge in an existing system will find its way to the heat pump's plate heat exchanger, which has far narrower waterways than a boiler's. The system will need thorough cleaning, treatment and in-line filtration before commissioning — plan for it rather than discovering it.

The cylinder

An existing boiler cylinder will almost certainly have too small a coil. With only 50 °C available instead of 75 °C, the heat transfer surface must be much larger — typically about 3 m², following the heat pump and cylinder makers (MIS 3005-D). Reusing a boiler cylinder produces very long reheat times and pushes the customer onto the immersion heater.

The customer

Discuss how the system will run at survey stage, not at handover. Someone used to a boiler expects rapid, hot bursts of heat and expects to switch the system off when out. A heat pump behaves quite differently, and a customer who has not been prepared for that will read normal operation as a fault.

Setting the expectation early prevents complaints that cannot be resolved technically, because there is nothing wrong with the system.

The numbers worth carrying into an exam

FigureValue
Ground extractionoutput − electrical input
Collector lengthextraction (W) ÷ extraction rate (W/m)
Bufferrequired total volume − emitter circuit volume
Horizontal yield (sanity check)10–40 W/m² of ground
Borehole yield (sanity check)20–55 W/m of borehole
Loop lengthAbout 100 m in 25 mm; about 400 m in 40 mm
Borehole100–150 mm diameter, 15–200 m deep, spaced ≥5 m
Pond loop≥3 m depth, about 9 m² surface per kW
Trench depthAround 1.2 m; CIBSE 0.8–2.0 m, preferring 1.5 m
Horizontal area at 1 m centresArea in m² equals pipe length in m
Heat pump cylinder coilTypically about 3 m² (follow the makers)
Boiler pipework at 20 K vs heat pump at 5 KAbout a quarter of the flow

Where this goes next

The survey says it can be built. Module 5 is the building of it — bases and clearances, pipework and insulation, laying and testing the collector, and the brine circuit.

📝 10-Question Mock Test

Click an option to see whether you got it right. Explanations appear instantly — no submitting at the end.

Your score: 0 / 10
Question 1 of 10
Design peak heat loss is 8 kW at a 45 °C flow temperature. Units are available at 6.2, 8.4 and 10.5 kW at that condition. Which should be selected?
Question 2 of 10
What does B0/W45 mean on a manufacturer's data table?
Question 3 of 10
A 9 kW ground source unit runs at a COP of 4. How much heat must come from the ground?
Question 4 of 10
An array is sized at 338 m of 25 mm pipe. How should it be installed?
Question 5 of 10
What is the minimum spacing between vertical boreholes?
Question 6 of 10
Why does an undersized horizontal array risk frost heave?
Question 7 of 10
Which measure most directly addresses structure-borne noise from an outdoor unit?
Question 8 of 10
Why must meltwater drainage be considered when siting an air source unit?
Question 9 of 10
Roughly how does the flow rate of a heat pump system at 5 K ΔT compare with a boiler system at 20 K for the same load?
Question 10 of 10
A single item on the pre-installation checklist fails. What is the correct response?

Practise the survey on the PlumbMate heat pumps course

Survey work is judgement plus arithmetic, and both improve with repetition. The heat pumps course gives you: