Halfway through a fit-out the clientโ€™s representative asks for two extra basin positions that are not on the drawings. He is pleasant, he is clearly senior, and he says just get them in, we will sort it out later.

The short answer

If you get them in, you will be sorting it out for months. A variation order records an agreement with the client to alter the work, and it must be agreed and approved in writing before the work is carried out.

Behind that sits a question that answers most site arguments: who is actually allowed to tell me that? The client is whoever commissioned and pays for the work, not whoever is standing nearest.

Three kinds of client

Key figures for clients, the chain of command and getting a change in writing
The examinable numbers from this article, in one place.

In one week you might work for three completely different people and never notice the difference until something goes wrong.

A private customer engages you directly — a homeowner, a landlord, someone having a bathroom done. The relationship rests on trust, because they cannot judge the pipework themselves. They may work through a representative or managing agent, who instructs, approves and pays on the owner's behalf. And if the property is let, the tenant is the end user: you liaise with them for access and keep them informed, but they did not commission the work and cannot approve the price or vary the job.

A contracting customer is another business that engages your firm under a contract. On a school where your firm is a subcontractor, the main contractor is your contracting customer — not the county council that owns the building, and not a council officer who happens to be visiting. They expect an organised workforce, usually a method statement before you start, and normally a CSCS card for everyone on site.

An internal customer is a department of your own organisation. A housing association with its own maintenance plumbers is the classic case: the housing office logs the repair, so your client is the housing office, even though a tenant lives in the flat and will be the one you meet.

Type of clientWho approves and paysWhat they expect of you
Private customerThe owner, or a managing agent acting for themDirect communication, a quotation, tidy work, a proper handover
Contracting customerThe company that holds your contract, usually the main contractorCards, risk assessments and method statements; work to programme
Internal customerThe department in your own organisation that raised the jobWork to the companyโ€™s own procedures and reporting; records kept

Naming the client is not paperwork for its own sake. It answers the only question that matters when somebody asks for something extra. On the school, the answer for the council officer is no. On the let house, the answer for the tenant is no. On the housing association job, the answer for the tenant is again no — but you still keep them informed, because you are standing in their kitchen.

The chain of command

Flow chart showing who may authorise a change to the work on a domestic job and on a contract
On a contract the authority is named in the contract. It is never the occupant or another trade.

An apprentice notices the electricians fixing a cable tray exactly where the drawings show the 54 mm heating flow and return. The temptation is to ask them to move it, or to drop the pipes under and redraw it later. Both are wrong, and for the same reason: neither the apprentice nor the electrician has the authority to change the design or to instruct another trade.

A chain of command is the formal reporting line that says who instructs whom. Instructions travel down it and problems travel up it. On a site two chains meet: the contractual one — client, main contractor, subcontractor — and your own company's.

The rule that follows is short: take instructions only from your own line, and pass everything else up it. The apprentice reports the clash to the plumbing supervisor. The supervisor speaks to the electrical supervisor and site management, and if the design has to change, that comes back down as a proper instruction. Nobody wins an argument in a riser.

The same rule catches the visitor with a clipboard. A council officer, a facilities manager or an architect may all ask for something perfectly reasonable. If they are not in your contractual chain, you refer the request rather than carry it out.

Building services work is never done alone, so one authority — normally the principal contractor — controls the overall programme, and each trade is expected to be aware of its dependencies and, where it can, to make direct contact to co-ordinate. Two supervisors agreeing on Monday who gets the riser on Tuesday saves a week.

What it is not is a licence to renegotiate the drawings between two operatives. The test is simple: am I agreeing a sequence, or am I changing the job? Agreeing a sequence is co-ordination; changing the job is a variation. If you are unsure which, treat it as a variation and ask.

Spoken, written and drawn

Comparison of spoken and written communication on site
Spoken communication is faster; written communication is the only kind you can produce later.

A customer catches you at the van and asks for the towel rail to be moved and a bigger basin fitted. You say that should be fine. Six weeks later she is refusing to pay for the basin because, she says, you never told her it would cost extra. You did tell her. Neither of you can prove anything.

Speech is fast, personal and good for anything that needs a reaction: agreeing access times, a toolbox talk, a call to say you are running late. It is also how you find out that you have not been understood, because you can ask a question and check. Its weakness is that it leaves no record.

So the rule is fixed: verbal communication is always backed up with written confirmation. Anything about your job, however casual it sounded, counts as formal communication.

The written trail runs from first contact to final payment:

Some information cannot be said at all. Working drawings carry the plans, elevations and details, scaled and dimensioned, that let a contractor price and then build the job. A sketch on a scrap of plasterboard settles an argument about a pipe route in ten seconds where a paragraph would fail.

MessageBest methodBecause
Running twenty minutes latePhone callImmediate, and the customer can respond
Agreement to extra time and costWritten confirmationIt is a change to money and to the programme
Where the pipe run goesDrawing or marked-up planPosition and size cannot be described reliably in words
A hazard everyone must know aboutSafety memo, backed by a briefingSame message to everybody, and a record that it was issued

Adjust the method to the person. For a customer with a hearing impairment, use written notes or drawings to reinforce what you say. For someone with a visual impairment, give more verbal detail and describe any diagram. Where English is not the person's first language, use short sentences and plain words, avoid slang and trade nicknames, back it up with a diagram, and ask a question to check you have been understood.

Ordering and checking materials

Second fix starts on Monday. On Friday somebody signs for a pallet without looking at it. On Monday the pallet turns out to hold fifteen basin traps and no basins, the merchant says the delivery note was signed as correct, and four plumbers stand about being paid to do nothing. That is not bad luck. It is two ordering mistakes and one signature.

On a larger contract there is a buyer, whose job is to source and purchase — obtaining quotes for the quantities required, together with delivery times and quality assurances. The route runs: requisition → purchase order → delivery → delivery note and invoice. Ordering outside that route — the phone call to the merchant that nobody records — is how a job ends up with materials it did not price and cannot charge for.

Materials are ordered against the work programme, so they arrive when the gang arrives. On larger sites, just-in-time delivery puts materials at the exact location at a time coinciding with the plumbers starting.

Get it wrong in either direction and it costs. Late materials mean idle labour, and if material is not available, labour costs increase. Too early, and you are storing expensive goods where theft is a real risk — which is why deliveries are best arranged early in the morning when operatives are there to receive them.

A delivery note should be checked against what is physically on the pallet and signed only if the two agree.

  1. Count and identify what has arrived — sizes and specification, not just item names.
  2. Compare it with the note and with what was ordered.
  3. Inspect for damage before the driver leaves.
  4. Note any shortage or damage on the note before signing, or refuse the item.
  5. Tell the supervisor immediately if anything affects the programme.

Signing an inaccurate note is the expensive mistake, because you have just recorded in writing that everything was correct. And even where a delivery arrives on time, the wrong goods have the same effect on the job as no goods at all.

If the merchant substitutes a different make or material, that is not a decision for the operative. The specification is part of the contract, and changes are made only after agreement with management. A substitution may affect cost, jointing, compatibility or compliance. The same applies to quantity: taking four fewer radiator valves because that is what turned up is a change to the job made by nobody in particular.

Plant deserves the same care. Hire runs whether the item is used or not, so off-hire it the day you finish, check it is complete before you sign, and report at once anything that arrives with a missing guard, a torn label or an out-of-date inspection tag — that item cannot be used until it is put right.

Variation orders

The five stages of a variation order from identifying the change to building it
The order is fixed: nothing is built until the priced change has been accepted in writing.

Nearly every construction project changes during design and construction, so most contracts contain a variation clause. A variation is a change, modification, alteration or amendment to the original contract and to how the works are to be carried out.

The order of events is fixed, and doing it in this order is the whole point:

  1. The change is identified and its effect analysed — on the other trades, on the programme, on cost.
  2. The change, including any change to the agreed contract price, is agreed and approved in writing by the client.
  3. A variation order is issued, including details of both cost and time.
  4. Only then is the work carried out.

So the answer on the fit-out floor is: obtain a written variation order through the contracts manager. A verbal request from someone who may not hold contractual authority is not a basis for extra work, and a price agreed verbally is not a price at all.

The single most important item in the written confirmation is the client's agreement to the extra time and the extra cost. Around that sit the description, who asked for it, the date, the drawing reference it alters, and any effect on other trades. Getting agreement early saves money, because the slow part of a variation is reaching agreement at all.

Cause of variationExampleWho normally bears the cost
Client relatedChange of plans, scope or specification after signingThe client
Design team relatedErrors or omissions in design; a change by the consultantDealt with through the design team
Contractor relatedDefective workmanship; unavailability of skills or equipmentThe contractor
OtherWeather, differing site conditions, changes in regulationsAs the contract provides

A variation may also be raised against you. If the clerk of works finds a run of exposed pipework unacceptable and it alters the agreed design, that too has to be discussed with the contractor, and the reasons and the effect on time and cost put to the customer.

Site procedures

A gang arrives at half past seven to start first-fix soil stacks. The temptation is to unload and get on. What actually has to happen first is a short list, and every item on it exists because somebody was hurt when it was skipped.

Everyone entering a construction site must sign in, wear the identification issued, and sign out again on leaving. Everyone must also have had a site induction: that site's hazards, rules, traffic routes, welfare facilities, alarm and emergency arrangements, and who is in charge of what. Site-specific PPE is stated at induction and worn from the gate.

Starting is a formal step, not just the moment you pick up a saw. The working space, the continuity and the flow of work are assessed, checked against the overall method statement and accepted; only then may work commence. Operatives must be trained, skilled and where required certified, and clear instructions given on the methods to be used. Some work needs more: a permit to work for hot works, confined spaces, live services and roof work.

A toolbox talk is a short, informal meeting — usually ten minutes, usually before the day's work — dealing with one matter of health and safety. Ten minutes on a new press-fit tool and its jaw-change procedure is a toolbox talk; so is a briefing before connecting to a live sewer.

The talk is not decoration. It is one of the ways an employer meets its legal duty to provide such information, instruction, training and supervision as is necessary, and it is normally recorded with the names of those present.

A safety memo is a short written notice to everyone affected, used where the same message must reach a lot of people accurately and be on record. Where the message is urgent or complicated it is backed by a spoken briefing, because a notice on a board is not proof that anybody read it.

MethodWho it reachesTypical use
Site inductionEvery person before they first work on the siteSite rules, hazards, welfare, emergency arrangements
Toolbox talkOne gang, from their own supervisorOne task or hazard, briefly, before the work
Safety memoEveryone affected, in writingA change or a newly found hazard, on record
Site meetingSupervisors and managers of each tradeProgress, sequence, co-ordination, problems

Sites also run work quality management systems: agreed checks at agreed stages, recorded as they are done. The point is the same as with safety paperwork. If the check was not recorded, then as far as the job is concerned it did not happen.

🔢 The numbers worth memorising

The client is
whoever commissioned and pays โ€” not whoever is nearest
A tenant
is the end user, not the client
A subcontractorโ€™s client
the main contractor
Instructions
come down your own line; problems go up it
The test on site
agreeing a sequence is co-ordination; changing the job is a variation
Verbal agreements
always backed up in writing
Quotation against estimate
a quotation is fixed; an estimate can move
Ordering route
requisition → purchase order → delivery → note and invoice
Delivery note
checked against the goods and signed only if they agree
Variation order
agreed in writing before the work, stating cost and time
Before work commences
space and sequence checked against the method statement and accepted
Toolbox talk
about ten minutes, one hazard, recorded with names

⚠️ Where people go wrong

  • Taking an instruction from whoever is standing nearest.
  • Letting a tenant approve or vary the work.
  • Instructing another trade, or moving a pipe run to avoid an argument.
  • Carrying out a request from someone outside your contractual chain.
  • Agreeing extra work verbally and pricing it later.
  • Ordering off-programme, or by an unrecorded phone call.
  • Signing a delivery note that does not match the pallet.
  • Accepting a merchantโ€™s substitution without going up the chain.
  • Starting a variation before the written order exists.
  • Leaving the effect on time out of a variation order.
  • Unloading and starting before induction and sign-in.
  • Starting a task before the area and sequence are accepted.
  • Treating a toolbox talk as decoration rather than a legal duty.
  • Relying on a notice board without a briefing.

📝 10-Question Self-Test

Straight from the Level 3 course question bank. Click an option to see whether you got it right — the explanation appears instantly, and there is nothing to submit.

Your score: 0 / 10
Question 1 of 10
What is the term for a customer who has work done in their own home and pays for it themselves?
Question 2 of 10
An instruction to a work supervisor to change the type of equipment used on a contract should NOT be given as?
Question 3 of 10
A private customer asks for a major addition to the quoted works. What is the most important item to include in the written confirmation?
Question 4 of 10
For a job carried out for a private customer, which one of these is normally the final item of written communication?
Question 5 of 10
A wall in a first floor flat is to be chased, and the only access is through the shared hallway and staircase. Which measure best protects the building fabric?
Question 6 of 10
In what state should the system be left at handover?
Question 7 of 10
A large housing association employs its own maintenance plumbers. One of them is sent to replace a leaking cylinder in a flat the association owns, the job having been raised by the association's own housing office. In terms of the client relationship, the housing office is best described as which type of customer?
Question 8 of 10
During a commercial fit-out the client's representative asks the Level 3 plumber on site to add two extra basin positions that are not on the drawings. Before starting the extra work, the correct course of action is to:
Question 9 of 10
A trade supervisor gathers the plumbing gang for ten minutes at the start of a shift to go through the safe use of a new press-fit tool and the manufacturer's jaw-change procedure. This is an example of which communication method, and which legal duty does it help the employer to meet?
Question 10 of 10
An apprentice plumber notices that a cable tray being fixed by the electricians runs exactly where the drawings show the 54 mm heating flow and return. Following the site chain of command, the apprentice should:
← Back to the Unit 336 guideLevel 3 Site Procedures and Planning: the Unit 336 Guide Next in Site procedures →Who Does What on Site: Design Team, Cost, Management and Craft Levels

Going further: the lessons behind this article

This article is the public answer. Unit 336 of the Level 3 course takes the same ground to the depth the exam and the synoptic assignment ask for, in 6 lessons:

  • Types of client: private, contracting and internal
  • The chain of command: who can give you an instruction
  • Spoken, written and drawn: choosing the right method
  • Ordering plant and materials, and checking what arrives
  • Variation orders: pricing a change the client asks for
  • Site procedures: inductions, toolbox talks and safety memos