Three questions come at a supervisor in the same morning. Can we run the heating in a different pipe material? Will the roof timbers carry a 300 litre cylinder? Where exactly is the oil storage tank going?

The short answer

Each has an obvious person to ask, and asking the wrong one wastes a day. Architect, structural engineer, surveyor — in that order.

And one distinction runs through the whole subject: the design team question is who knows; the chain of command decides who tells you. None of these people give you an instruction directly.

The design team

Key figures for who does what on site
The examinable numbers from this article, in one place.
Table of roles on the client's side and the contractor's side of a building services job
Two sides, two reporting lines. Instructions come down your own.

The architect is normally the leader of the design team, turning the client's requirements into a building design and working drawings, and generally overseeing the construction work until handover. Because the architect owns the design, anything that changes what the building is goes to them.

So a change of pipework material is an architect's question, because it affects the specification, the appearance and possibly the contract. So is the layout of the fire compartments — which walls and floors are compartment lines, and therefore where you may not pass a pipe without a proper fire seal.

QuestionAsk
Can we change the pipework material?Architect
Where are the fire compartments?Architect
Will these roof timbers take the load?Structural engineer
Where should the oil storage tank go?Surveyor
What was the design flow temperature for this circuit?Building services engineer
Is this setting-out line correct?Site engineer

Knowing the difference saves you from a common and expensive error. If a joist is in the way of a pipe run, notching it is not a plumbing decision, because a notch in the wrong place weakens the member. In the same way, a pipe passing through a compartment wall is not simply a hole; it is a penetration in a fire barrier. Both are cases where the person holding the tool is not the person who decides.

Cost and quantities

Two money questions on one contract: what does a change of press-fit system do to the price, and can the firm be paid for the 800 metres of pipework installed? These sound like the same question. They go to two different people.

The estimator prices work before it happens. They break the bill of quantities into labour, materials and plant, apply a rate to each, then add a percentage for overheads — site offices, site and administration salaries — and a percentage for profit. That total is what the company tenders.

So a question about the cost of a change of materials is an estimator's question: they hold the build-up — the rate assumed for that fitting, the labour allowed for the joint, the plant assumed.

The quantity surveyor is the cost professional for the project. Before the work they measure from the architect's drawings and produce the bill of quantities that contractors price. During the work they measure what has actually been installed and value it, so the contractor can receive interim payments. At the end they prepare the final account. And the QS values variations.

Estimator first, quantity surveyor after: the estimator says what it should cost, the QS says what it did.

Between the two sits the buyer, who turns the priced allowance into actual goods at actual prices. If the buyer cannot get the specified item at the rate the estimator allowed, that difference is a real cost and has to be raised, not absorbed quietly on site.

Both roles depend on your records. Interim payments, variations and the final account are all built from measured quantities and dated records. A gang that does not record what it installed is a gang whose company gets paid late, or less.

It also explains why an estimator's allowance is not a target you should quietly beat by cutting corners. The rate assumes the joint is made properly, in the material specified, with the fixings named. Work that is faster because it is not the work that was priced is not a saving; it is a defect waiting for the clerk of works.

Running the job

On a large development the gang deals with perhaps five people in a week and could not reliably say who any of them works for. That matters, because two of them represent the client and three represent contractors, and they want different things from you.

The clerk of works is appointed to represent the client on quality. They check and verify work as it is completed — workmanship and materials — against the drawings and specification, keeping written records of the sample checks they make, and keep a diary against future disputes. If somebody independent is inspecting your pipework section by section and writing down what they find, that is the clerk of works.

The project manager is responsible for the overall co-ordination and delivery of the project. On smaller schemes there may be no separate appointment, and the duties are shared between the architect and the quantity surveyor.

RoleWorks forCares most about
Clerk of worksThe clientQuality of workmanship and materials
Project managerThe client or the projectCo-ordination and delivery of the whole project
Contracts managerThe contractorThe contract, variations, commercial matters
Construction manager or site agentThe contractorDay-to-day running of the site and the programme
Health and safety managerThe contractorInspections, records, investigations, training
Trade supervisorThe trade contractorThat trade’s operatives, work and quality

Two confusions cost marks and cause arguments. The first: the clerk of works checks quality, the quantity surveyor checks cost, and neither does the other's job. The second: the principal designer advises and assists the client and the team with their duties under health and safety legislation, while the designer prepares the detailed design — neither of them runs the site.

There are also visitors who work for nobody on the job: the building control officer from the local authority, checking compliance with the Building Regulations; the water inspector employed by the water undertaker; and the health and safety inspector, who can arrive unannounced.

Craft levels and allocating work

Qualification levels and the supervision that goes with each
Supervision loosens as the qualification rises, but delegation always follows competence.

A vented cylinder needs replacing on Thursday. You have a first-year apprentice, a Level 2 plumber and a Level 3 plumber. Somebody has to be in charge, and the answer is not whoever is free.

LevelWhat they may doSupervision
Apprentice or traineeLearn the trade; simple tasks as experience growsFull supervision at all times
Level 2 qualifiedNon-complex hot and cold water, sanitation and basic heating pipeworkRegular supervision; passes problems up
Level 3 qualifiedRun their own jobs, including unvented; deal with client enquiries and complaintsSupervises themselves and other staff
SupervisorDesign and installation across systems; overall responsibility for operativesHolds at least Level 3, normally with years of experience

So the cylinder job goes to the Level 3 plumber, who can supervise themselves and the apprentice. A Level 2 plumber has limited self-responsibility and is not there to carry an apprentice; an apprentice is never left in charge, even of work that is on their syllabus.

The single test when deciding who gets a task is competence: whether that person can do that job safely and correctly. Not how long they have been with the firm, not how fast they are, not how much they charge.

Direct supervision means somebody competent present and watching. It is required where the task is new to the person, where the risk is high, where the work is on a system that cannot be made safe, or where an operative is young or newly arrived. As experience is demonstrated, supervision loosens — but it is loosened deliberately, not by default.

Competence is checked, not assumed: confirm qualifications and cards, confirm any specific certification, watch the person work, and record the result. A supervisor is expected to identify the competence levels needed and assess the training requirements of each team member.

Supervision is not only allocation. Where somebody has made a mistake, the effective approach is to talk it through privately, agree where it went wrong and agree an action plan. Discussing work problems with staff motivates them; threats, deducting pay, cutting breaks and public criticism demoralise them and produce a subdued, silent workforce that stops telling you things.

Some problems are not yours to solve. A grievance about pay, a safeguarding concern, a health condition, or an employee showing signs of possible substance abuse must be passed to suitably qualified staff — the employer, occupational health or HR. Untidiness, an unsigned toolbox talk record and a request to change hours are ordinary supervisory matters; suspected substance abuse is not.

🔢 The numbers worth memorising

Design change
architect; load-bearing capacity, structural engineer
Position of plant on a property
surveyor
The systems you install
designed by the building services engineer
Estimator
prices work before it is done, plus overheads and profit
Quantity surveyor
measures and values work after it is done
Clerk of works
the client’s eye on quality, with written sample records
Apprentice
full supervision at all times
Level 3
supervises themselves and others
Allocating work
on competence, checked and recorded

⚠️ Where people go wrong

  • Asking the architect about loads, or the engineer about the specification.
  • Notching a joist because it is in the way.
  • Treating a compartment wall as just a hole to drill.
  • Sending a quantities question to the estimator, or a pricing question to the QS.
  • Beating an estimator’s allowance by not doing the work that was priced.
  • Confusing the clerk of works with the quantity surveyor.
  • Expecting the principal designer or the designer to run the site.
  • Putting a Level 2 plumber in charge of an apprentice.
  • Allocating on availability rather than competence.
  • Loosening supervision by default rather than deliberately.
  • Criticising an operative publicly instead of agreeing an action plan privately.
  • Handling a suspected substance abuse concern on site yourself.

📝 10-Question Self-Test

Straight from the Level 3 course question bank. Click an option to see whether you got it right — the explanation appears instantly, and there is nothing to submit.

Your score: 0 / 10
Question 1 of 10
On site, what level of responsibility does an apprentice hold?
Question 2 of 10
A building services supervisor needs to discuss the difference in cost caused by a change of materials on a contract. Who would they speak to?
Question 3 of 10
With whom would a building services supervisor discuss how much material has actually been installed on a job?
Question 4 of 10
Which of the following activities has to comply with BS 7671, Requirements for Electrical Installations?
Question 5 of 10
About the load-bearing capacity of roof timbers, who would a building services supervisor consult?
Question 6 of 10
Smaller firms taken on by a managing construction company to carry out work for it are called?
Question 7 of 10
Who would a building services supervisor consult about the effect of changing the type of pipework to be installed?
Question 8 of 10
Who would a building services supervisor talk to about where an oil storage tank is to be installed on a job?
Question 9 of 10
On a building services contract, which level of qualification would the site supervisor most typically hold?
Question 10 of 10
On a heat pump installation the client employs an independent person to check and verify the pipework and plant as each section is completed, keeping written records of the sample checks made. Which job role is this?
← Previous in Site proceduresClients, the Chain of Command and Getting a Change in Writing Next in Site procedures →The Act, CDM, the Regulations Under Them, and the Certificates

Going further: the lessons behind this article

This article is the public answer. Unit 336 of the Level 3 course takes the same ground to the depth the exam and the synoptic assignment ask for, in 4 lessons:

  • The design team: architect, engineers and surveyor
  • Cost and quantities: estimator and quantity surveyor
  • Running the job: managers, clerk of works and supervisors
  • Craft levels and allocating work: who supervises whom