Build the change first and you have no agreed basis for recovering the money or the time.

The short answer

A variation is any change, modification, alteration, revision or amendment to the original contract and to how the work is to be carried out. However small it looks, it must be recorded and authorised in writing by whoever holds contractual authority before it is built. Three things go in the record every time: what is changing, why, and who authorised it.

Why a small change is not a small matter

Key figures for variations
The examinable numbers from this article, in one place.

You are half way through first fix when the client says the en-suite basin would look better on the opposite wall. About 4 m of extra pipework. Friendly client, small change, and the temptation is to run the pipe and sort the paperwork later.

The drawings and the specification are the contract. They are what you priced. Anything departing from them changes what you are owed and, very often, when you can finish. Build it first and you have no agreed basis for recovering either. Nearly every construction project meets a change, which is why most contracts contain a variation clause — a term saying in advance how changes will be instructed, priced and recorded.

Where variations come from

Grid of variation causes against who usually carries the cost
The cause points at the cost, which is why the record names what changed and why.

Four families of cause, and they point at who is likely to carry the cost:

SourceTypical causes
Owner or clientChange of plans or scope, change of specification, change of schedule, indecision holding up a decision
Consultant or designerErrors and omissions, ambiguous or inadequate details, conflicts between contract documents, a design change
ContractorDefective workmanship, lack of co-ordination, unavailable skills or equipment, poor planning
OtherWeather, differing site conditions, safety considerations, a change in government regulations

That last group matters: a variation is not always somebody's fault. A change in the Building Regulations part way through a long contract is nobody's error, but it is still a change to the work.

Who can authorise one

Flow chart showing who may authorise a change to the work
An apprentice asked for a change on site records it and passes it up. They do not decide.

Only the person who holds contractual authority. On a private domestic job that is the customer who is paying. On a contract it is whoever the contract names — typically the architect or contract administrator, sometimes the client's representative or the main contractor's project manager. It is never the occupant, never another trade's foreman, and never the operative who was asked.

So when a client asks an apprentice for a change on a Tuesday afternoon, the apprentice's job is not to decide. It is to stop, record what has been asked, and pass it to the supervisor. Any departure from the contract drawings or specification goes through change control before it is built.

The wrong answers are worth naming, because they are the ones people reach for. Running the pipe and putting the hours on a daywork sheet leaves you claiming for work nobody instructed. Refusing outright because the drawings were signed off at tender stage is also wrong — contracts anticipate change, that is what the variation clause is for. And an apprentice's sketch handed to the client is not an agreed record of anything.

The variation order

The five stages of a variation order, covering both cost and the revised completion date
Price the change, state the new completion date, get it accepted, then build it.

A variation order is the document that records an agreement made with a client to alter the work specified in a building contract. Any variation changing the agreed contract price must be agreed and approved in writing by the owner before the variation order can be put into action.

Crucially it covers both cost and time. A change nearly always pushes the finish date, and if the order says nothing about that, the contractor has quietly accepted the same completion date with more work in it.

  1. The change is identified and recorded — what is being asked for, and by whom.
  2. The effect is analysed: extra labour, materials and plant, and the knock-on effect on the rest of the programme.
  3. A priced variation quotation is issued, showing the extra cost and the revised completion date.
  4. The client accepts it in writing.
  5. Only then is the work carried out, and the programme updated.

A verbal agreement on the doorstep leaves nothing to show when the customer disputes the final account six weeks later. Written communication gives a permanent record; settling the price at final account stage invites an argument over both the money and the delay. An instruction to change what is used or how it is done should come as a letter, a signed variation order or a site instruction form — never as a verbal request.

Who bears the cost

For private work, the general rule: if the customer suggests changes after the contract has been signed, the customer bears the costs of the delay and of the additional material and design. But the reverse holds too — if the variation is caused by poor installation or an inability to complete a task properly, the contractor could be liable. If the clerk of works decides the routing of exposed pipework is not acceptable, that alters the agreed design and the contractor pays to put it right.

Written quotations usually carry an exclusions section listing what the price does not cover — making good plaster, lifting fitted carpets, removing asbestos. Exclusions protect the contractor only for what they actually name. If a private customer's job turns out to include items not specifically listed in the exclusions, the company bears the extra cost — not the customer's insurer, not the merchant, not the local authority. A vague exclusions list is a bill waiting to happen.

Getting agreement early also saves money in its own right: one of the real costs of a variation is the time the whole agreement process takes while the gang stands about waiting to know what to build.

Materials: three changes in disguise

The specified product cannot be got

The specification calls for a particular make of thermostatic mixing valve; the merchant now quotes six weeks and offers an equivalent. An alternative is normally permitted, provided the performance, functional and visual aspects of the design can be assured — and deciding that is the designer's job, not the merchant's. The supervisor checks the alternative against the specified performance and gets written approval before ordering. A supplier's assurance that something is like for like is not approval. The substitution is a variation, and the written approval records what was fitted and why.

Fitting it on the merchant's word transfers the risk to you. Leaving the valve out for snagging hands over an incomplete system. Ordering the specified valve anyway protects the specification and wrecks the date.

The building is not as drawn

The builder's opening for the boiler flue is 150 mm out of position and cannot be used as drawn. The rule is blunt: any discrepancy — an out-of-tolerance substrate, edge, surface or opening — should be reported immediately, before undertaking subsequent operations. Not at the weekly progress meeting, not after the boiler is on the wall.

The reason is partly technical and partly commercial. Core-drilling a new hole or shifting the appliance may breach the flue clearances shown on the drawings. And the moment you build over somebody else's error without reporting it, the error becomes yours.

The delivery is damaged

Materials from third parties are inspected on receipt to confirm the delivery is what was ordered or specified, and to confirm as far as reasonably possible its quality, viability, conformity and type. The documentation is checked and the delivery signed for — sign for what arrived, not for what the note says arrived.

The same applies to client-supplied materials: the same inspection and acceptance or rejection as for the contractor's own. So when a client's sanitaryware is unpacked and one basin is chipped and the WC pan has a hairline crack, the supervisor rejects the damaged items and refers them to the client and the supplier immediately. Damaged items are discarded, clearly labelled and kept separate from sound goods so they cannot be fitted by mistake.

Fitting them anyway makes the contractor responsible for appliances that were already defective. Replacing them quietly from your own stock and adding them to the invoice is an unauthorised variation. Stopping all work until the client buys a new suite is a wild over-reaction to two damaged items.

In all three cases the answer is the same shape: stop, report, get it agreed in writing, then build. What changes is who you report to — the designer for a substitution, the main contractor or clerk of works for a discrepancy, the client and supplier for damaged goods.

🔢 The numbers worth memorising

Variation
Any change, modification, alteration, revision or amendment to the contract
The record
What is changing, why, and who authorised it
Variation order
Covers both extra cost and the revised completion date
Approval
In writing by the owner before the order is put into action
Client change after signing
Normally at the customer cost
Contractor-caused change
Contractor liable for the subsequent costs
Discrepancy
Report immediately, before undertaking subsequent operations

⚠️ Where people go wrong

  • Doing the extra and putting it on a daywork sheet,You are claiming for work nobody instructed. Get it authorised first.
  • Refusing because the drawings were signed off,Contracts anticipate change — that is what the variation clause is for.
  • Taking the instruction from the occupant or another trade,Only whoever holds contractual authority can vary the work.
  • Pricing cost but not time,A variation order states the revised completion date too, or you have accepted the old one.
  • Relying on a vague exclusions list,Anything not specifically listed becomes the company cost.
  • Accepting a merchant word that a product is equivalent,Substitution needs the designer written approval on performance, function and appearance.
  • Working over a builder error,Report it before the next operation, or the error becomes yours.

📝 10-Question Self-Test

Straight from the Level 3 course question bank. Click an option to see whether you got it right — the explanation appears instantly, and there is nothing to submit.

Your score: 0 / 10
Question 1 of 10
A private customer's job changes to include items that were not specifically listed in the exclusions section of the company's written quotation. Who bears the extra cost?
Question 2 of 10
Halfway through a first fix, the client tells the site supervisor they now want the en-suite basin moved to the opposite wall, adding about 4 m of pipework. The change is not on the drawings or in the contract. What should the supervisor do before the pipework is run?
Question 3 of 10
The specification calls for a particular make of thermostatic mixing valve, but the merchant reports a six-week lead time and offers a different make it says is equivalent. The programme cannot wait. How should the supervisor deal with this materials change?
Question 4 of 10
A client has asked for an additional outside tap and a second radiator, both outside the original quotation. Which process correctly secures agreement to the extra time and cost before the work is carried out?
Question 5 of 10
An operative finds that the builder's opening for the boiler flue is 150 mm out of position and cannot be used as drawn. The operative suggests core-drilling a new hole and carrying on. What does BS 8000-0 say should happen with a discrepancy of this kind?
Question 6 of 10
A plumbing subcontractor is held up by others and is then asked to carry out extra work that was never priced. Which document records the extra labour and materials so they can be charged?
Question 7 of 10
A client asks for a second radiator after the programme has been agreed. How should the extra work be priced and confirmed?
Question 8 of 10
Part way through a long contract the regulations change, and the flue termination detail shown on the drawings will no longer comply. Is this a variation?
Question 9 of 10
The clerk of works decides that the routing of a run of exposed pipework is not acceptable, although it matches the drawing. What should follow?
Question 10 of 10
The client’s representative gives a supervisor an instruction on site to move a plantroom pump set. Which of these is an acceptable written confirmation of that instruction?
← Previous in Site proceduresMethod Statements: Purpose, Headings and Use on Site Next in Site procedures →Monitoring Safety and Cost: Induction, Permits and Wastage

Going further: the lessons behind this article

This article is the public answer. Unit 336 of the Level 3 course takes the same ground to the depth the exam and the synoptic assignment ask for, in 3 lessons:

  • Variations: what counts as a change to the contract
  • Variation orders: pricing extra time and extra cost
  • Materials changes: substitutions, discrepancies and damaged goods