Commissioning is confirming and correcting, not recording. The paperwork matters — MCS audits fail on it regularly — but the paperwork is the residue of a process, and a form filled in on a system nobody actually checked is worse than no form at all.

This article covers Module 6 of the PlumbMate solar thermal course: what to check before a drop of fluid goes in, flushing filling and purging, cold fill pressure and proving the freeze protection, setting the controller and verifying flow, and what the customer goes away with. There is a 10-question mock test at the end.

Before you commission

MIS 3001 requires commissioning to follow a documented procedure with a completed checklist. Working to memory is how steps get missed, and missing commissioning records, such as no glycol concentration, pre-charge or flow rate written down, are among the most common non-conformities found at MCS audit — usually on a system that works perfectly well.

The pre-fill checks

Then isolate the pump before filling begins, so it cannot be started dry. And have the fluid safety data sheet on site before opening the drum — it is the document that tells you the PPE and the spillage procedure, and it is no use in the van.

Everything on that list is easy to reach now. After filling, half of it is under pressure and hot.

Flushing, filling and purging

The nine commissioning steps as a grid of cards, each with the kit for that step: 1 flush and fill with pre-mixed fluid through the filling station; 2 purge the air until the return runs clear; 3 pressure test just below the relief valve setting, about 30 minutes, joints bare; 4 set the cold fill pressure and its red marker; 5 set the controller; 6 set and record the flow rate on the flow meter; 7 run it hot, check the joints again and vent; 8 insulate the joints; 9 prove the glycol with a refractometer and record it. Before step 1, the pre-fill checks; after step 9, label the plant and hand over.
Commissioning, in order: write each figure down as you go.

Air is the enemy of a solar primary. It collects at high points, blocks circulation, causes noise, and corrodes. Removing it properly at commissioning avoids most of the callbacks a new system generates in its first season.

The order

  1. Flush and fill with the pre-mixed fluid through the filling station.
  2. Purge the air.
  3. Pressure test with the fluid in, never air: just below the relief valve setting for about 30 minutes, or to the maker's figure, with every joint inspected and still bare.
  4. Set the cold fill pressure.
  5. Set the controller.
  6. Set and record the flow rate.
  7. Run it hot, check the joints again and vent.
  8. Insulate the joints.
  9. Prove the glycol with a refractometer, and record it.

Flushing

Flush the circuit, with the fluid the manufacturer specifies, to remove flux residues, swarf, jointing compound and debris. Most solar makers flush with the heat transfer fluid itself, because water left in the collectors dilutes the glycol; flush with water only where the maker allows it and the circuit can be drained completely before the final fill. Debris left behind ends up in the pump, the flow meter and the narrow passages of the heat exchanger — all places it is expensive to remove later.

Filling and purging

Fill with the correct pre-mixed fluid from its container using a filling and flushing station, so no mains water goes into the circuit. If you use the mains at all, to flush with water where the maker allows it, do it through a temporary connection with backflow protection and disconnect it afterwards — a filling loop left coupled is a Water Regulations contravention. Run the station to circulate at a velocity high enough to sweep air along with the flow to the vents. Purge until the fluid runs clear and free of bubbles and the flow through the meter is steady, not surging.

A filling and flushing station purging a solar circuit, shown twice. Left, not yet: the return hose pours into the station's tank full of bubbles and foam, and the flow meter's float is surging. Right, purged: the return runs clear with no bubbles, and the flow meter is steady. A note underneath says never fill a hot collector: fill early, late, or under a cover.
Watch the return, not the clock: purged when it runs clear and the flow through the meter is steady.

The hydraulic test

Once the circuit is filled and purged, and before it is dressed and insulated, pressure test it with the fluid in, never air: take it to just below the relief valve setting and hold it for about 30 minutes, or to the maker's figure, while you inspect every joint, still bare. Anything weeping is fixed and then the circuit is retested. A repair is not accepted on the strength of having been made, and a second leak sitting behind the first is common enough that the retest is a step in its own right.

Only then insulate the runs, and leave the joints you can reach uncovered until they have been checked again after the first heat cycle. Covering a joint before then means taking the insulation off again to find the leak.

Fluid

Use the correct pre-mixed concentration, and keep the pump isolated until the circuit is full. Never fill a hot collector: filling in the early morning, in the evening, or under a cover avoids flashing the fluid to steam and being scalded.

Pressure, glycol and freeze protection

Setting the pressure

Fill to the design cold-fill pressure, which comes from the static height of the system plus a margin — roughly a tenth of a bar per metre of height, plus typically half a bar. The margin is what keeps the highest point positively pressurised, so air cannot be drawn in and the fluid cannot boil at low pressure on a hot afternoon.

Record the figure, because every future pressure check is measured against it. A gauge reading means nothing on its own and a great deal against the value the system was left at.

Verify the safety devices

Confirm the pressure relief valve operates and that its discharge terminates safely and visibly, into a container that can take hot glycol and steam. A discharge hidden away means a system can lose pressure and freeze protection all summer with nobody noticing until the first hard frost splits a collector.

Prove the glycol

This is the last step: once the system has run hot and the joints are insulated, test the concentration with a refractometer and record the freezing point achieved. A typical target is protection to around −20 °C, but the real requirement is what the fluid manufacturer specifies for the location. Do not judge by colour or by how much went in — a refractometer reading is a number you can write down; "we put antifreeze in" is not.

More is not better. Raising glycol concentration reduces the specific heat capacity and increases viscosity, so the circuit carries less heat per litre and the pump works harder to move it. Over-concentrating quietly reduces the system's output while appearing perfectly healthy.

Normal pressure variation

A solar circuit's pressure moves by a few tenths of a bar between cold and hot in normal running, and more after it has stagnated. A reading taken on a hot afternoon and compared against a cold fill figure will always differ, and that difference is not a fault. Compare like with like, or allow for the swing; a swing much bigger than the commissioning record shows points at the vessel.

Check for leaks under pressure

Inspect every joint, connection and component once the circuit is at working pressure and has been through a heat cycle. Joints that are sound cold can weep once thermal movement has worked them, so a leak check before the system has ever been hot is only half a check.

Setting the controller and verifying flow

The differential

Typical settings, measured as the collector sensor minus the store sensor, are a switch-on difference of 6–8 K and a switch-off difference of 2–4 K. The gap between them — the hysteresis — is what prevents the pump short-cycling on and off around a single threshold. Set them too close and the pump hunts; set switch-on too high and useful low-level gain is thrown away.

The maximum store temperature

Set the store limit so the controller stops charging before the cylinder overheats, typically around 60–65 °C. This is a protection setting, not a comfort one, and it must be consistent with the scald protection at the outlets — the store can be hotter than is safe at a bath, which is what a thermostatic mixing valve at the outlet, not at the cylinder, is for.

Set and record the flow rate

With the cold fill pressure and the controller set, run the pump and set the flow rate to the design figure using the flow meter, and record it. A typical flow rate is about 0.6 L/min per m² of collector, with 0.5 at the low end and 0.7 at the high end; the maker's figure governs. MIS 3001 asks for a means of accurately indicating the flow rate, and its example checklist records the setting, which is the value every future performance question is measured against.

Vent again once hot

Run it hot, check the joints again, and vent. Dissolved air comes out of solution as the fluid warms, so a system vented cold will have more air in it an hour after it starts running. Then insulate the joints. That second vent is what separates a system that settles down from one that generates a callback in week three.

Observe operation

Let it run and confirm the pump starts and stops at the set differentials, that flow direction is correct, and that the temperature rise across the collector, flow minus return, is sensible.

Then set the auxiliary heat source to fire in the late afternoon or evening, so solar has the whole day to contribute first. Getting this backwards is a common reason a technically sound installation underperforms — and nothing on it is broken.

Records, handover and the customer

What must be recorded

Documents to hand over

Manufacturer instructions for every component, the system schematic, the commissioning record, warranty documents, the recommended maintenance schedule, the performance estimate produced by the MCS calculation, and the Building Regulations compliance certificate where the work is notifiable, which it always is for an unvented cylinder. Where MCS applies, the MCS certificate too; it is a different document from the compliance certificate and both may be needed. Under MIS 3001 the customer also gets the details of the heat transfer fluid (what it is, its hazards, its life and how to dispose of it), the lowest temperature the freeze protection covers, a signed declaration that the installation meets MIS 3001, the recommended interval for the first inspection, and a decommissioning plan.

The two documents a service depends on

Label the plant

Put labels at the pump station, at the cylinder connections and at any isolation point someone could reach. Between them they should say what fluid is in the circuit and its fill pressure, where to isolate it, and which pipes run hot, plus the two labels MIS 3001 requires: your contact details as installer, and a warning that the pump station or relief valve may discharge. This prevents two common maintenance errors: topping up with the wrong fluid, and grabbing pipework far hotter than a heating circuit.

The demonstration

Show the customer how to read the controller, where the isolation points are, what normal operation looks like, and what to do if something seems wrong.

Above all, explain seasonal variation: excellent summer output, a useful contribution in spring and autumn, and little in midwinter. A customer who has not been told this reads entirely normal December behaviour as a fault — and that callout is not a technical problem, so it cannot be fixed technically.

What comes next

Module 7 is maintenance and fault finding: routine servicing to BS 5918, stagnation and fluid degradation, and a method for working a fault from the symptom — including the callouts that turn out not to be faults at all.

📝 10-Question Mock Test

Click an option to see whether you got it right. Explanations appear instantly — no submitting at the end.

Your score: 0 / 10
Question 1 of 10
What must happen to the pump before filling begins?
Question 2 of 10
A joint weeps during the hydraulic test and is remade. What happens next?
Question 3 of 10
Why must a hot collector never be filled?
Question 4 of 10
A system's collectors are 7 m above the pump station and a 0.5 bar margin is required. What is the cold fill pressure?
Question 5 of 10
A system was left at 1.2 bar cold and reads 1.45 bar on a hot July afternoon. What does that indicate?
Question 6 of 10
A refractometer shows protection to −8 °C where the fluid manufacturer requires −20 °C. What is the correct action?
Question 7 of 10
What are the two consequences of over-concentrating the glycol?
Question 8 of 10
Why must the system be vented again after it has run and warmed up?
Question 9 of 10
When should the auxiliary heat source be timed to fire?
Question 10 of 10
Which documents are essential when maintaining a solar system for the first time?

Commissioning is where a solar system either becomes maintainable or does not. Every number written down — cold fill pressure, flow rate, freezing point, the two differentials — is a value some future engineer will measure against. A record that says "commissioned, all OK" gives them nothing.

And the last conversation matters as much as the first. Seasonal variation explained at handover is a customer who understands their system; unexplained, it is a callout in December on a system that is working exactly as designed.