Two years after handover a tenant complains of smells in a ground floor flat. The maintenance contractor wants to know what the stack was tested at, who tested it and what the seals read on the day.

The short answer

If there is no record, everybody guesses and somebody pays. When a client asks for evidence that the work has been tested and meets the required standard, what they are handed is the commissioning records. Delivery notes, a manufacturer's manual and a signed quotation prove purchase, description and price — none of them shows a test result.

And one notice has a deadline attached that people miss: before repairing, reconstructing or altering a drain you must give 24 hours notice to the local authority under Section 61 of the Building Act 1984.

The commissioning record

Key figures for records, handover and notification for sanitation work
The examinable numbers from this article, in one place.

BS 8000-13 does not stop at requiring the tests. It requires final testing, making good and recording of results in accordance with the specification and any statutory requirements, including the period of notice for inspection.

EntryWhy it is there
Date and time of commissioningFixes when the system was proved and starts any guarantee period
Names of the operatives who installed and testedTraceability β€” somebody has to be answerable for the figures
Location and identification of the systemWhich block, which riser, which section was tested
Manufacturers and types of componentsSpares, filters and service intervals can be found later
Soundness test resultsThe pressure applied, the duration held and the outcome
Performance test resultsWhich appliances were discharged, and the seal remaining in each trap
Defects found and rectified, and any retestShows the system passed as finally left, not as first tested

On a commercial above ground system, the entries that belong on the record are the ones about the work itself: the completion date and the names of the plumbers who did the installation. The depth and gradient of the public sewer, the name of the building control officer and the merchant's delivery notes are not commissioning data.

On a large installation the records end up with the facilities manager as part of the operation and maintenance manual; on a domestic job they go in the customer's file. Either way the tests may need to be witnessed by building control, and the record is what they sign against.

Records also feed forward. Where a system is altered later, the original record is the reference the next plumber works from: it says what was there, what it was tested at and what it achieved.

Write them as if a stranger will read them, because a stranger will. "Stack 3 tested, OK" helps nobody. "Stack 3, levels 1–6, air tested 38 mm wg, held 3 min, no drop; performance test, WC + basin + sink level 6, minimum seal remaining 34 mm at level 5 basin" answers the question two years from now.

Handing over

A document giving instructions for operation, maintenance and use of the waste water discharge system and the sanitary appliances shall be prepared and made available for the building owner or occupier. And on site: make sure any operation, cleaning or maintenance instructions provided for the user are intact and, where applicable, attached to the installation.

The file the customer gets:

For a macerator, a lifter or a disposal unit, the operating instructions are the item that matters most: they tell the user what can and cannot go down the unit, how to isolate it and what maintenance it needs. A pedestal wash basin, a low level WC suite and a wall hung urinal need no operating instructions; a macerator does.

Documents on their own are not a handover. Walk the customer round and show them:

Ten minutes at handover is cheaper than a callout.

Protective coverings on sanitary appliances are kept in place as long as practically possible, up to handover, and any appliance chipped, cracked, scratched or distorted is replaced rather than patched. So the protective tape comes off only once the system has been tested and is being handed over — not before the fittings are offered up, not as soon as the water is on, and not when the sealant is applied.

Handover is also the moment to examine every appliance and fitting for damage and satisfactory operation before the customer sees it. It is far cheaper to change a chipped basin now than after the customer has signed for it.

And tell the customer what to expect and what to watch for — a macerator that runs on after a flush, a gurgling basin, a smell that appears when a particular appliance is used. Give them who to call and the record reference. Explain any drainage arrangement needing their attention: a property served by a cesspool should be checked for overflow every two weeks.

Notifying building control

The routes for notifying building control about sanitation and drainage work
Which route you take depends on whether you hold a scheme registration.

Sanitary pipework and drainage are controlled services, so putting them in, extending them or materially altering them is building work. Most building work must be notified to a building control body in advance, unless it will be self-certified by a registered competent person, or it is exempted from notification.

RouteWhat it involvesWhen it suits
Full plans applicationDetailed drawings and specification deposited with the local authority and checked before work startsLarger or more complex work, where the client wants approval on paper first
Building noticeA notice that work is about to start. No plans deposited; the work is inspected as it progressesSmaller work that needs to get under way quickly
Initial noticeGiven jointly with an approved inspector, who takes on the building control functionWhere a private approved inspector is used rather than the council

Under the building notice route the authority is told work is about to start, inspects as it goes, and notifies you if the work does not comply. It is quicker and less detailed than a full plans application, but you carry the risk of being told to open something up.

It is not necessary to notify in advance of work carried out by a person registered with a competent person self-certification scheme for that type of work. Where the work is self-certified, within 30 days of completion the occupier is given a certificate confirming compliance, and the building control body is given a notice of the work carried out — both normally issued through the scheme operator.

Two exceptions. Where the work is an emergency repair there is no need to delay it to give advance notice where that is not practicable; the work must still comply, and notice must be given at the earliest opportunity. And work in the schedule of non-notifiable minor work must still comply but need not be notified.

Notification is not only a start-of-job matter. Final testing and recording must accord with the specification and any statutory requirements, including the period of notice for inspection — if the inspector is entitled to witness your air test, you have to give them the notice period to turn up.

Which Part covers what

PartWhat it covers
AStructure
BFire safety, including fire stopping where pipes pass through separating elements
FVentilation, including bathroom extract
GSanitation, hot water safety and water efficiency
HDrainage and waste disposal, including sanitary pipework
JCombustion appliances and fuel storage, including hearths
LConservation of fuel and power
PElectrical safety in dwellings, including solar photovoltaic

Two of those catch people out. The requirements for hearths beneath heating appliances are in the Building Regulations — not BS 5440, not the Gas Safety (Installation and Use) Regulations, not BS EN 12828. And a solar photovoltaic installation is chiefly a Part P matter, because it is an electrical installation.

The 24 hour notice

Repairs, reconstruction and minor alterations to drains and sewers are not normally covered by the Building Regulations themselves, but local authorities have other powers over them — and material alterations to existing drains are covered by the Regulations.

Under Section 61 of the Building Act 1984, any person intending to repair, reconstruct or alter a drain must, except in an emergency, give 24 hours notice to the local authority. Where the work is done in an emergency, the work must not be covered over without giving that notice. The person doing the work must also give the local authority free access to inspect it.

The notice exists because the authority has real powers if the work is wrong:

Disused drains draw the authority's interest for a reason: they give rats a route between the sewer and the surface, and they can collapse and cause subsidence. Sealing them is a duty, not a courtesy.

And responsibility runs wide. The designer, the builder and the installer must ensure the work complies — and the building owner may also be responsible, and may be served with an enforcement notice. That is why the notification and the record matter to you personally, not just to the client.

🔢 The numbers worth memorising

Evidence of testing
the commissioning records, not delivery notes or a quotation
Record entries
date and time, operatives, location, components, soundness and performance results
Protective coverings
stay on up to handover
Damaged appliance
replaced, not patched
Three routes in
full plans, building notice, initial notice
Competent person scheme
certificate to the occupier and notice to the BCB within 30 days
Drain work
24 hours notice under Section 61 of the Building Act 1984
Emergency drain work
must not be covered over without that notice
Disused drain
sealed where the authority directs (Section 62)
Cesspool
checked for overflow every two weeks

⚠️ Where people go wrong

  • Offering delivery notes or a quotation as evidence of testing.
  • Writing β€œtested, OK”. Write the pressures, the durations and the seals remaining.
  • Putting the sewer depth or the inspector’s name on a commissioning record.
  • Handing over a folder without walking the customer round the system.
  • Stripping protective coverings before handover.
  • Patching a chipped appliance instead of replacing it.
  • Self-certifying without scheme registration.
  • Missing the 30 day deadline for the compliance certificate and the BCB notice.
  • Covering over emergency drain work before notice is given.
  • Leaving a disused drain unsealed.
  • Testing without giving the specified period of notice for inspection.
  • Looking for hearth requirements in BS 5440 or the Gas Safety Regulations.

📝 10-Question Self-Test

Straight from the Level 3 course question bank. Click an option to see whether you got it right — the explanation appears instantly, and there is nothing to submit.

Your score: 0 / 10
Question 1 of 10
Before any air test is applied, what does BS EN 12056-2 National Annex NG.2 require the final inspection of a completed discharge system to confirm?
Question 2 of 10
Which test pressure and duration does Approved Document H paragraph 1.38 set for the air test of sanitary pipework, fittings and joints?
Question 3 of 10
An installer who is not a member of a certification scheme fits a new sanitary system in a dwelling. Who has to be notified?
Question 4 of 10
On completing the testing of a new above-ground drainage installation, what does BS 8000-13 clause 4.1.1 require in addition to carrying out the tests themselves?
Question 5 of 10
A plumber is putting a WC and a wash basin into a new ground floor cloakroom, with a new branch connection to the existing discharge stack. Why is this notifiable building work?
Question 6 of 10
A householder wants the drainage alterations for a new utility room to start next week and does not want to pay for drawings to be prepared. Which notification route suits, and what does it involve?
Question 7 of 10
A developer wants the drainage and sanitation design for a block of flats checked and approved on paper before any work is committed to on site. Which route should be used?
Question 8 of 10
A contractor wants a private firm rather than the council to carry out the building control function on a drainage job. What has to be given, and by whom?
Question 9 of 10
The installer carrying out a sanitation job is registered with a competent person self-certification scheme for that type of work. What does that change about notification?
Question 10 of 10
Sanitation work has been self-certified by an installer registered with a competent person scheme. What must the occupier of the building be given, and by when?
← Previous in Sanitation systemsCommissioning Sanitary Pipework: Inspect, Air Test, Performance Test Next in Sanitation systems →On Site: the Walk Round, the Air Test and Finding the Leak

Going further: the lessons behind this article

This article is the public answer. Unit 334 of the Level 3 course takes the same ground to the depth the exam and the synoptic assignment ask for, in 4 lessons:

  • What a sanitation commissioning record must contain
  • Handing over: the documents and the demonstration
  • Notifying building control: notices, full plans and competent persons
  • Building Regulation Parts and the notice the law requires for drain work