A site agent points at your drawing and asks two questions. Who says the kitchen sink waste has to be 40 mm, and where does all this water end up?

The short answer

Both answers come out of a short list of documents. Requirement H1 of the Building Regulations is the law (in Northern Ireland, Part N); Approved Document H is the guidance that shows how to satisfy it; and BS EN 12056 is the code of practice, not the law.

Everything else follows from two ideas: every trap must retain at least 25 mm of water seal under working and test conditions, and an unventilated branch has a maximum length that gets shorter as the gradient gets steeper.

The documents, and where the water goes

Key figures for sanitary pipework
The examinable numbers from this article, in one place.

H1 says an adequate system of drainage shall carry foul water from appliances within the building to a proper outfall. Section H1 is foul water drainage, H2 wastewater treatment and cesspools, H3 rainwater drainage.

BS EN 12056 comes in five parts: general and performance, sanitary pipework (Part 2 — the system types and the calculations), roof drainage, wastewater lifting plants, and installation, testing and maintenance. Approved Document H names it as an alternative way of meeting H1, and records that System III is the type traditionally used in the UK.

Foul water means waste from a sanitary convenience or bidet, waste from an appliance used for washing foul receptacles, and water used for food preparation, cooking or washing. H1 sets the outfall in order of priority: a public sewer first; then a private sewer connecting to one; then a septic tank with secondary treatment; and only where none of those is practicable, a cesspool.

Below ground, three arrangements: a combined system carries foul and surface water in one shared sewer; a separate system keeps them apart, the surface water discharged without any treatment to a watercourse or soakaway; a partially separate system takes most surface water separately but allows a little into the foul drain.

Surface water is sized on area, not appliances. A pitched roof becomes an effective design area by multiplying the plan area by 1.29 at 30°, 1.50 at 45° and 1.87 at 60°. A roof 8 m long measuring 4 m in plan at 45° gives 32 m², and 32 × 1.50 = 48 m².

ApplianceWaste or branch size
Wash basin, bidet32 mm
Bath, shower, sink, washing machine, dishwasher, urinal bowl40 mm
Food waste disposal unit, branch serving two to four basins50 mm
WC with outlet under 80 mm75 mm
WC with outlet over 80 mm100 mm

Those are nominal sizes: a pipe called 40 mm measures about 42 mm outside and a 100 mm soil pipe about 110 mm, which is why a bath waste is written 40/42 mm and a WC branch 100/110 mm.

A house with one WC never needs calculating; a block of flats does. Above-ground pipes are sized on discharge units (DU): add the discharge units of everything the pipe serves, then Qww = K √∑DU, where K is the frequency factor — 0.5 for a dwelling or office, 0.7 for a school or hotel, 1.0 for congested public use, 1.2 for special use. Do not confuse discharge units with loading units, which size cold water supply pipes.

Traps and seals

A bottle trap
A bottle trap: easy to clean, but it blocks more readily than a tubular one.
Trap seal depths by appliance and the 25 mm that must remain
The depth fitted varies. The depth that has to survive does not.

A tenant complains of a drain smell that comes and goes. You put a dip stick in the basin trap and it reads 20 mm where it should read 75.

Every point of discharge must have a trap so foul air cannot enter the building, and under working and test conditions every trap must retain at least 25 mm of water seal. That 25 mm is the pass mark; the seal it starts with is deeper.

ApplianceTrap diameterSeal depth
Wash basin, bidet32 mm75 mm
Bath, shower40 mm50 mm
Sink, urinal bowl, food waste disposal unit, washing machine, dishwasher40 mm75 mm
WC pan, outlet under 80 mm75 mm50 mm
WC pan, outlet over 80 mm100 mm50 mm

Two relaxations. A basin seal may drop to 50 mm only on a spray tap basin with a flush grated waste and no plug. And where a bath, shower or flat-bottomed appliance discharges directly to a gully, the seal may be reduced to not less than 38 mm.

The four ways a seal goes

What makes self-siphonage worse: a funnel shaped appliance, the length, gradient and diameter of the branch, the type of trap and the grid at the outlet, an overflow connected into the trap, sharp bends, and whether the branch is vented.

P traps are the default on a primary ventilated system, with the branch the same diameter as the trap. Bottle traps should only be used on wash basins. Resealing and anti-vacuum traps are made for unventilated small bore branches; they need regular inspection and can be noisy, so they are a remedy, not a first choice.

Access matters as much as the seal. If the trap is part of the appliance, the appliance must be removable; every other trap must be fitted directly after the appliance and be removable or fitted with a cleaning eye. Where a waste pipe runs to a gully at ground level it must finish through the grating but above the water level of the trap seal — never below the water and never onto the top of the grating.

The branch limits

Maximum unventilated branch lengths by pipe size and gradient
Steepen the gradient and the permitted length falls — which surprises people.

In a primary ventilated stack system, all the appliances are closely grouped around the discharge stack, and the stack itself does the ventilating. There are no separate ventilating pipes, which is why the pipe is called a soil and vent pipe. Previously the single stack system, and the arrangement behind BS EN 12056-2 System III.

It only works if the pipework is disciplined: appliances close to the stack; P traps with the branch the same diameter as the trap; bends and junctions avoided where possible and made with a large radius where they cannot be; and the stack run straight with a large radius bend at the base.

BranchDiameterMaximum lengthGradient
Wash basin or bidet32 mm1.7 m18 to 22 mm/m
Wash basin or bidet32 mm1.1 m18 to 44 mm/m
Wash basin or bidet32 mm0.7 m18 to 87 mm/m
Basin, bath, shower, sink, washing machine40 mm3.0 m18 to 44 mm/m
Two to four basins, urinals50 mm4.0 m18 to 44 mm/m
WC, outlet over 80 mm100 mm6.0 m18 mm/m or more

The figure to give for an unventilated 100 mm WC branch is 6 m, laid at 18 mm/m (about 1 in 55) or steeper. (Approved Document H Table 2 now allows an unventilated 100 mm branch serving up to eight WCs to run 15 m; the 6 m figure comes from the earlier code of practice and remains the one to give.)

Notice what the basin rows are telling you. Steepen the gradient and the permitted length falls, because a steeper pipe runs full more readily and siphons the trap: 32 mm at 22 mm/m may run 1.7 m; at 44 mm/m only 1.1 m; at 87 mm/m only 0.7 m.

So for a basin at 2.6 m from the stack, the first option is not a vent and not a special trap: it is to increase the diameter. Take the branch to 40 mm and 3 m is allowed. Flattening it below 18 mm/m is not the answer, because the pipe stops being self-cleansing.

And where a horizontal 40 mm waste sags between two clips, it holds water in the dip, loses its fall and stops being self-cleansing. The remedy is to re-clip the pipe at the correct centres — for plastics: 32 to 40 mm, 0.5 m horizontal and 1.2 m vertical; 50 mm, 0.6 m and 1.2 m; 75 to 100 mm, 0.9 m and 1.8 m.

Cross-flow and the no connection zone

A first floor bath fills with dirty water whenever the WC on the opposite side of the stack is flushed. Nothing is blocked — the two branches have been connected opposite one another.

The rule is short: a branch pipe should not discharge into a stack in a way which could cause cross-flow into any other branch pipe. BS EN 12056-2 turns that into geometry: the smaller branch should be connected at or above the centre line of the larger connection, or at right angles or less to it, or at least 200 mm below it.

Every branch creates a no connection zone on the opposite side of the stack, and no other branch may have its centre line inside that zone (a centre line may sit exactly on the boundary). The zone gets taller as the stack gets bigger: 90 mm on a 75 mm stack, 110 mm on 100 mm, 210 mm on 125 mm and 250 mm on 150 mm, together with a 200 mm dimension that does not change with stack diameter.

Making the connection itself:

A near horizontal entry with a tight radius is the worst case for another reason: it produces the greatest suction below the branch inlet, and suction below an inlet is what empties the traps underneath it.

Boiler condensate may be connected to sanitary pipework: at least 22 mm pipe through a 75 mm condensate trap, preferably into an internal stack, and where it goes into a branch, downstream of any sink waste connection. The pipework must resist a pH of 6.5 and lower.

Ventilated branches and secondary ventilated stacks

An architect has put a WC 8 m from the stack. Once a branch passes its unventilated limit there are only three legitimate answers: a branch ventilating pipe to external air, a branch ventilating pipe to a ventilating stack, or an air admittance valve.

So for that WC at 8 m, the acceptable arrangement is a ventilated branch. A stub stack is no help — it is limited by height above the drain invert, not by branch length. A combined system is a below ground arrangement and has nothing to do with a branch at all.

A branch ventilating pipe is:

Read the three system names as a sequence and they stop blurring:

On a secondary ventilated system the cross-connections slope upwards from the discharge stack, at up to 67.5°, so water cannot get into the vent. The lower end connects below the lowest branch connection and above the bend at the base; the upper end joins the stack vent or passes through the roof. A ventilating stack serving dwellings up to 10 storeys is at least 32 mm; on a ventilated branch system, where the stack only collects branch vents, 30 mm is usually enough.

The stack itself

Diagram of a primary ventilated stack system
One stack, no branch vents — the arrangement most domestic work uses.
Stack sizeMaximum capacity
50 mm (no WCs)1.2 l/s
65 mm (no WCs)2.1 l/s
75 mm (max one small outlet WC)3.4 l/s
90 mm5.3 l/s
100 mm7.2 l/s

A stack serving urinals is at least 50 mm; serving WCs with outlets under 80 mm at least 75 mm; over 80 mm at least 100 mm. The internal diameter is never less than the largest trap or branch connected to it, and it must not reduce in the direction of flow. The dry stack vent above the highest branch may be reduced in one and two storey houses but not below 75 mm.

The bend at the foot is where back pressure is made. Give it as large a radius as possible and at least 200 mm at the centre line, or use two 45° bends. Then keep branches away from it:

A ground floor WC may drop straight into the drain instead, but only where the depth from floor level to the drain is 1.3 m or less.

An offset in the wet part of a stack makes pressure trouble on both sides: suction below it and positive pressure above. Avoid them. Where unavoidable in a building of not more than three storeys, allow no branch connection within 750 mm of the offset. Over three storeys a ventilating stack may be needed, cross-connected above and below. An offset above the topmost branch does not need venting.

A stub stack is a short stack, closed at the top with an access fitting or AAV, taking ground floor appliances into the drain. It is allowed only where it connects into a ventilated discharge stack or a ventilated drain not subject to surcharge, and where no connected WC has a floor level more than 1.3 m above the invert of the drain connection, and no other branch has its centre line more than 2 m above that invert. It is also one honest answer for a customer who wants an extra ground floor WC that cannot reach the existing stack.

Air admittance valves and terminations

A developer building 19 houses wants an AAV in every loft, so no stack goes through a roof. That is allowed, but not on its own.

An air admittance valve is a one-way valve to BS EN 12380. Negative pressure lifts a diaphragm and lets air in; when the pressure equalises the diaphragm drops back, so foul air cannot get out. That lets a ventilated discharge stack terminate inside the building.

The advantages sell themselves to a builder: less pipework, no roof penetration and so no route for water ingress, no foul smells indoors, and more freedom in the design.

Where it may and may not go:

Neither Approved Document H nor BS EN 12056-2 sets a height for an AAV. The often quoted 1 m above the spill-over level is a manufacturer's rule of thumb, not a rule from a standard.

And there are places an AAV must not be relied on: it must not reduce the ventilation the below ground system needs; it should not be used where the drain has an interceptor trap or is subject to surcharge, because both need an open pipe to relieve positive pressure; and it must not be the only ventilation on a system serving a septic tank or cesspool.

So, the 19 houses. The below ground system must be ventilated by a flow of air — a ventilating pipe at or near the head of each main drain, and an open ventilating pipe, with no AAV on it, on any drain fitted with an intercepting trap or subject to surcharge. (You may still hear "one open stack in five", or open pipes at the head and midpoint for 11 to 20 dwellings. Those came from the withdrawn BS 5572; BS EN 12056-2 contains no dwelling count. Give the Approved Document rule.)

Where the stack does go to open air it finishes at least 900 mm above any opening into the building within 3 m, with a wire cage or perforated cover that does not restrict air flow — metallic in rodent control areas. Two consequences: a vent pipe finishing level with an openable window is acceptable only if it is at least 3 m away horizontally; and where it stays within 3 m, 900 mm above the opening is the least height it may terminate at.

🔢 The numbers worth memorising

The law and the standard
Part H is the law; BS EN 12056 is the code of practice
UK traditional system
BS EN 12056-2 System III
Outfall priority
public sewer → private sewer → treatment system → cesspool last
Roof area factors
1.29 at 30°, 1.50 at 45°, 1.87 at 60°
Frequency factor K
0.5 dwelling, 0.7 school or hotel, 1.0 congested, 1.2 special
Minimum seal retained
25 mm under working and test conditions
Seal depths
basin and sink 75 mm; bath, shower and WC 50 mm
Direct to a gully
seal may reduce to 38 mm
32 mm basin branch
1.7 m at 22 mm/m, 1.1 m at 44, 0.7 m at 87
40 mm branch
3.0 m; 50 mm 4.0 m; 100 mm WC 6.0 m
Plastics clip spacing
32–40 mm 0.5 m / 1.2 m; 50 mm 0.6 / 1.2; 75–100 mm 0.9 / 1.8
Cross-flow rule
at or above the centre line, at right angles or less, or 200 mm below
No connection zone height
90 / 110 / 210 / 250 mm on 75 / 100 / 125 / 150 mm stacks
Branch vent
within 750 mm of the trap, 25 mm (32 mm over 15 m or five bends)
100 mm stack
7.2 l/s; stack vent never below 75 mm
Base bend
at least 200 mm radius at the centre line
Lowest branch above the invert
450 mm to three storeys, 750 mm to five
Stub stack
WC 1.3 m, other branches 2 m above the invert
AAV
BS EN 12380, above the flood level, ventilated space, never outside
Open termination
900 mm above any opening within 3 m

⚠️ Where people go wrong

  • Calling BS EN 12056 the law. Part H is the law; the standard is guidance.
  • Confusing discharge units with loading units, which size cold water supply.
  • Working a pitched roof on its plan area without the slope factor.
  • Treating 25 mm as the seal a trap starts with. It is the minimum retained.
  • Fitting a bottle trap anywhere but a wash basin.
  • Running a waste pipe below the water level of a gully trap, or onto the grating.
  • Assuming a steeper branch may run further. The permitted length falls.
  • Reaching for a vent when a bigger branch would do.
  • Flattening a branch below 18 mm/m. It stops being self-cleansing.
  • Connecting a bath branch straight opposite a WC branch.
  • Reducing a stack in the direction of flow, or a stack vent below 75 mm.
  • Bringing a branch in too close to the base bend.
  • Treating a stub stack as an answer to a long branch. Its limits are heights above the invert.
  • Fitting an AAV outside, below the flood level, or in a dusty loft.
  • Quoting a 1 m height for an AAV. No standard sets one.
  • Relying on AAVs alone across a site. The drain still needs an open vent at its head.

📝 10-Question Self-Test

Straight from the Level 3 course question bank. Click an option to see whether you got it right — the explanation appears instantly, and there is nothing to submit.

Your score: 0 / 10
Question 1 of 10
Which figures are used when working out the size of above-ground discharge pipes?
Question 2 of 10
Air admittance valves are being fitted to every house on a development of 19 new dwellings. Where must an open ventilating pipe still be provided?
Question 3 of 10
A soil and vent pipe finishes at the same level as an openable window. How far, at minimum, must it be from that window?
Question 4 of 10
In England and Wales, how far below floor level is a soil stack permitted to go at most?
Question 5 of 10
A soil vent pipe terminates at the same height as an openable window. What is the minimum distance that must separate them?
Question 6 of 10
What is the longest unventilated 100 mm WC branch that may discharge to a primary ventilated discharge stack?
Question 7 of 10
A WC is to be sited 8 m from the discharge stack on a 100 mm branch. Which arrangement does Approved Document H Table 2 permit without a branch ventilating pipe?
Question 8 of 10
The presence of which drainage fitting means an air admittance valve should not be used?
Question 9 of 10
On a stub stack, how far may the highest waste connection be above the invert of the drain before the stack has to be ventilated?
Question 10 of 10
How should a waste pipe be arranged where it discharges into a gully at ground level?
← Back to the Unit 334 guideLevel 3 Sanitation System Planning and Design: the Unit 334 Guide Next in Sanitation systems →Macerators, Lifters, Wet Rooms, WC Flushing and Urinals

Going further: the lessons behind this article

This article is the public answer. Unit 334 of the Level 3 course takes the same ground to the depth the exam and the synoptic assignment ask for, in 7 lessons:

  • Sanitary pipework: the rules and the standard sizes
  • Traps, seal depths and how a trap loses its seal
  • Primary ventilated stacks: the branch limits that decide the layout
  • Joining branches to the stack: cross-flow and the no connection zone
  • Ventilated branches and secondary ventilated stack systems
  • Discharge stacks: sizes, the base, offsets and stub stacks
  • Air admittance valves, stack terminations and housing sites