How many floors of a twelve-storey block can the main serve on its own? About eight β€” and two of those are lost to friction. Everything above that is a design problem, and the undertaker will have opinions about how you solve it.

The short answer

A mains supply typically reaches a building at 3 to 7 bar, roughly 30 to 70 m head. Thirty metres lifts water about eight storeys, and friction in the pipework takes two of those back. A multi-storey building, for this purpose, is one with more than three floors.

Both BS EN 806-2 clause 15.1 and BS 8558 clause 4.3.48 give the same instruction: supply the lower floors from the main and pump only the floors where pressure is insufficient. The design question is what kind of help the upper floors get.

Direct boosting, and why suppliers dislike it

Key figures for cisterns in tall buildings
The examinable numbers from this article, in one place.

Pumps fitted straight onto the incoming supply pipe is direct boosting. It is permitted only where the pumped flow is less than 0.2 l/s (12 litres per minute) or the water supplier consents (BS 8558 Annex A.4) — and a pump drawing more than 12 l/min from a supply pipe is notifiable under Regulation 5.

Suppliers often refuse, and the reasons are good: a pump sucking on the main lowers the neighbours' pressure and raises the backflow risk. In practice direct boosting means small flows — a single top-floor flat, or a drinking water header.

Where it is allowed, something has to call the pumps. With a high-level storage cistern, a float switch starts them at about half capacity and stops them about 50 mm below float valve shut-off, so the float valve never closes against the pumps. On a mains-boosting set with no cistern, a pressure transducer on the discharge senses the fall as outlets open.

The break cistern, and what it buys you

A protected cold water storage cistern with its cover, warning pipe and float valve
A protected cistern: rigid cover, screened vent and warning pipe, and access to service it.
How to get water up a multi-storey building
The main gets you about ten storeys. Everything above that is designed.

For the rest of the block the supplier will ask for the layout in BS 8558 Annex A.2: the main fills a low-level break cistern through a float valve, and a booster set on its outlet pumps to a high-level storage cistern or into the boosted supply. This is indirect boosting, and it is the usual arrangement in a tall building.

With a break cistern there is no limit on pump capacity (BS 8558 clause 4.3.9), because the pumps no longer draw on the main. Four things follow: no surge on the main when the pumps start and stop, no backflow into the main, the neighbours keep their pressure, and there is a reserve for peak demand.

In a very tall building, intermediate break cisterns on service floors split the system into pressure zones, so no floor sees more pressure than its fittings can take.

Sizing it is a balance, and the balance is the exam question. Capacity is not less than 15 minutes of the pumps' maximum output — but the cistern must not be oversized, because standing water stagnates (BS 8558 A.2). The aim is rapid turnover. A low-level dry-run switch stops the pumps at about 225 mm above the suction connection (a figure from the withdrawn BS 6700; the pump set maker’s figure governs), so the cistern is sized above that level.

Drinking water at the top of the building

BS EN 806-2 clause 19.1.2 says potable water is taken directly from the main wherever practicable. Where outlets are above the height the main can reach, the drinking taps are fed from a cistern protected in accordance with 19.1.3.

The alternative is direct boosting to a drinking water header: a pipe high in the building holding 5 to 7 litres per dwelling for the kitchen sinks while the pumps are off (BS 8558 A.5), with a pipeline level switch to start the pumps as it empties and an automatic air inlet valve on the upstand.

The 25 mm steps that decide the levels

Schedule 2 paragraph 16(4) requires every storage cistern to have an overflow pipe with a means of warning of impending overflow, screening against insects, a cover excluding light and insects, and insulation. BS EN 806-2 clause 19.1.11 then scales that with capacity:

Read the stack from the water upwards and it makes sense. The warning pipe invert is at least 25 mm above the water level. The overflow invert is at least 25 mm above the warning pipe invert. So the water sits at least 50 mm below the overflow. And the inlet discharges at least twice its own diameter above the overflow, which is the type AG air gap.

BS EN 806-2 clause 19.1.8 says the same thing from the valve's side: it closes at least 25 mm below the warning pipe, or 50 mm below the lowest overflow where there is no warning pipe.

The warning pipe itself is at least 19 mm bore, rigid, never rising outside the cistern, discharging where the drip will be noticed, and able to carry the full inlet flow without submerging the inlet. Vents and overflows get corrosion-resistant mesh of 0.65 mm maximum aperture.

Filling a big cistern without hammering the main

A 10,000 litre cistern on a 6 bar main with an ordinary domestic float valve creeps open, dribbles for an hour and slams shut. Paragraph 16(1) asks for an effective adjustable valve, and a large cistern has better ways to provide one:

Linked and sectional cisterns

Where the volume will not fit in one cistern, use cisterns of the same size and capacity, as few as possible, and pipe them so no water short-circuits and stagnates (BS EN 806-2 clause 19.1.4; BS 8558 clause 4.3.12.1). Connect in parallel where possible with inlet and outlet at opposite ends; in series, link at the bottom and the middle and take the main outlet from the cistern furthest from the float valve. Every cistern gets its own float valve and servicing valve, all set to open and close at the same level, and its own warning pipe, never joined.

Over 1,000 litres there must be compartments or a standby cistern so the supply continues while one is cleaned (clause 19.1.10), and the inlet valve must be adjustable without removing the whole cover, with 350 mm clear over a conventional cistern and 500 mm over a large bolted-lid one.

Sectional cisterns are bolted up on site from 1 m² panels precisely because they can be made to fit the space — the panels go through the plant room door one at a time. Every large cistern gets a washout pipe at its lowest point discharging over a type AA air gap, and insulation to keep the water below 20 °C and never above 25 °C at any tap.

One last figure that is structural before it is plumbing: the base carries about 1 kg per litre. Twelve thousand litres is twelve tonnes on the floor.

🔢 The numbers worth memorising

Mains supply
3 to 7 bar, about 30 to 70 m head β€” roughly eight storeys, less friction
Multi-storey
more than three floors, for this purpose
Direct boosting limit
less than 0.2 l/s (12 l/min) without the supplier’s consent
Break cistern capacity
not less than 15 minutes of maximum pump output β€” and no more
Dry-run switch
about 225 mm above the suction connection
Drinking water header
5 to 7 litres per dwelling
Warning pipe
25 mm above the water level, minimum 19 mm bore
Overflow
25 mm above the warning pipe β€” so water sits 50 mm below the overflow
Inlet air gap
at least twice the inlet diameter above the overflow (type AG)
Screening mesh
0.65 mm maximum aperture
Access above the lid
350 mm conventional, 500 mm large bolted-lid
Stored water temperature
below 20 Β°C, never above 25 Β°C at any tap
Cistern weight
about 1 kg per litre β€” 12,000 litres is twelve tonnes

⚠️ Where people go wrong

  • Oversizing a break cistern β€œfor safety”. Fifteen minutes of pump output is a ceiling as well as a floor β€” beyond it the water stagnates.
  • Getting the 25 mm steps the wrong way round. Water level β†’ 25 mm β†’ warning pipe β†’ 25 mm β†’ overflow, so 50 mm from water to overflow.
  • Joining the warning pipes from linked cisterns. Each cistern gets its own, or you cannot tell which float valve is passing.
  • Fitting an ordinary BS 1212 float valve to a large cistern on a high-pressure main. It dribbles, then hammers β€” an equilibrium, pilot or delayed action valve is the answer.
  • Forgetting that a solenoid valve has no float of its own, and fitting one without a second high-level switch as backup.
  • Treating the base loading as somebody else’s problem. A tonne per thousand litres is a structural calculation before it is a plumbing one.

📝 10-Question Self-Test

Straight from the Level 3 course question bank. Click an option to see whether you got it right — the explanation appears instantly, and there is nothing to submit.

Your score: 0 / 10
Question 1 of 10
A servicing valve is required in which one of these positions?
Question 2 of 10
In which one of these positions should servicing valves be fitted?
Question 3 of 10
Refer to the diagram below. Which type of system does it show?
The drawing this question refers to
Question 4 of 10
A storage cistern holds somewhere between 1000 and 5000 litres. What is the smallest vertical separation permitted between the invert of the warning pipe and the invert of the overflow pipe?
Question 5 of 10
Because it offers little resistance to flow, which valve is normally chosen as the servicing valve immediately upstream of a float-operated valve?
Question 6 of 10
A cold water storage cistern with a base of 1,000mm x 800mm is to sit on a timber platform. What is the smallest size the platform may be cut to?
Question 7 of 10
Cold water for an industrial premises is to come from two storage cisterns coupled together. Which of these requirements applies?
Question 8 of 10
A three-storey office block has drinking water points on every floor. Which statement about its cold water supply is correct?
Question 9 of 10
Two cold water storage cisterns are to be linked together. How should they be connected?
Question 10 of 10
What should the sizing of a break cistern on a boosted cold water system aim to provide?
← Previous in Cold water systemsWho Do You Have to Tell? Regulation 5, Building Control and the Ten Working Days Next in Cold water systems →Booster Sets: Duplicate Pumps, the Pressure Vessel, and Which Switch Failed

Going further: the lessons behind this article

This article is the public answer. Unit 331 of the Level 3 course takes the same ground to the depth the exam and the synoptic assignment ask for, in 3 lessons:

  • Multi-storey supply: the mains limit and the break cistern
  • Large cisterns: warning pipes, overflows and inlet valves
  • Linked and sectional cisterns in the plant room