A joint you find on a walk-round costs a minute. The same joint found under test pressure, with the ceiling closed and the decorators in, costs a day.

The short answer

The sequence is fixed and the order carries the marks: inspect dry, then fill, then test. Water hides faults as much as it reveals them — once the system is full, every change means a drain-down, and a fault under pressure can damage finishes.

What the dry inspection is measured against

Key figures for inspect dry, fill slowly, test once
The examinable numbers from this article, in one place.

An inspection is only as good as the paperwork it is checked against. Before you start, have to hand:

The walk-round

The apprentice has finished the pipework and says it is ready to fill. You take the drawing and walk it, and within ten minutes you have found an open end behind the bath panel, a compression joint with no olive, and a cistern sitting on two loose boards. None of them would have survived the fill.

And the inspector you have to invite: the water undertaker must be given the opportunity to inspect, with prior notice before any statutory inspection or test (BS 8000-15 clause 4.1.1). Do it before the system is filled, so anything they want changed can be put right without a drain-down.

The trench is the one item that cannot wait. Once a service pipe is buried, the depth and the joints are invisible — so the underground run is inspected in the open trench and tested before backfilling as well. A groundworker who backfills to tidy the site has removed the evidence.

Extra checks by system type

SystemExtra visual checks
DirectStop valve and drain-off at entry; servicing valves to each appliance; any PRV fitted the right way round; backflow protection at hose taps, WCs, bidets and appliance connections
IndirectCistern base and support; screened warning pipe and overflow; insect-proof but not airtight cover; float valve and servicing valve on the inlet; gate valves on the distributing pipes; insulation on the cistern and roof-space pipes
BoostedBreak cistern and its float valve; duplicate pumps with isolating valves each side; low-level float switch for dry running; pressure switch or transducer; accumulator with its single connection, pre-charge and a check valve on its supply side; pressure gauges; electrical supply isolated until the system is full

The accumulator usually has one pipework connection: water enters and leaves through it, and the air side has only the pre-charge valve. The check valve on its supply side stops stored water flowing back into the supply pipe when the mains pressure drops.

What water goes in

A site agent offers the water bowser because the temporary mains connection is not in yet. The answer is no.

The system is filled with fluid category 1 water taken directly from the undertaker's main. Softened water, rainwater or bowser water would contaminate a system that is about to carry drinking water. BS EN 806-4 clause 6.1.1 adds that it should be drinking water free of particles of 150 µm or larger, which on large jobs means filling through a mechanical filter.

And one practical rule that catches people: do not fill a system until the drainage is connected, because you will not be able to flush it afterwards.

The initial fill is made at the system's normal operating pressure — the mains for a direct system, the head of the cistern for a distributing system, the pump set's working pressure for a boosted one. It is not the test pressure. The fill finds weeping joints at low pressure, where a joint can be remade after a local drain-down. The test comes later, from a test pump, once the system is full and settled.

Filling without air locks

The top-floor bathroom splutters, the loft cistern will not fill, and every joint is tight. Nothing is leaking. The distributing pipe has an air lock, and it got there during the fill.

Fill slowly, with the highest draw-off point open so air is expelled as the water rises. Every high point needs an air vent or an open tap, closed again once water shows.

On cistern-fed pipework there is a subtlety that explains the spluttering. Let the cistern fill to its working level first and let the float valve shut, then open the gate valves on the distributing pipes so the full head is available and the pipe fills at full bore. A trickle fill through a half-open valve is the classic way to trap air: the water creeps along the bottom of the pipe and leaves a pocket at every high point.

Water goes to the bottom; air goes to the top; the top has to be open. On a rising main the top is the cistern or the highest tap; on a distributing pipe it is the highest outlet on that pipe, which may not be the highest outlet in the building.

Large and multi-storey systems are filled section by section: leaks are found in a small area, air locks are less likely, and if something goes wrong only one section has to be drained. Station an operative at the main isolation valve so it can be shut the moment a leak is called.

The test pressure

How to pressure test cold water pipework in metal and in plastics
On plastics the gauge falls because the pipe creeps. That is not a leak.

Schedule 2 paragraph 12(1) requires the system to withstand an internal pressure of not less than 1.5 times the maximum pressure to which the installation is designed to be subjected in operation.

An installation designed for 3 bar is tested at 3 × 1.5 = 4.5 bar. A system on a 2 bar supply is tested at 3 bar. The maximum working pressure is normally the incoming mains pressure measured after any pressure reducing valve. The test covers the whole installation, not only the new section, and vulnerable components that cannot take the test pressure are removed and replaced with temporary pipe.

Rigid pipework: the one-hour test

Copper and stainless steel water pipework is rigid. It does not stretch appreciably, so if the gauge falls the water has gone somewhere.

First, fill the system and leave it about 30 minutes for the water temperature to settle. A temperature difference between the test water and its surroundings changes the pressure on its own: water expands as it warms, so a cold fill in a warm building would show a rise, which can hide a leak, and a warm fill in a cold roof space a fall, with nothing wrong anywhere. No regulation sets the 30 minutes; allow it on every rigid test, so that once the pump goes on the gauge only moves for a leak.

Then Schedule 2 paragraph 12(2)(a): pump the whole system to the test pressure; the test then continues for one hour without further pumping; the pressure is maintained; and there is no visible leakage throughout.

Plastics: why the gauge falls when nothing leaks

A polybutylene system pumped to 4.5 bar and left for an hour reads 4.1 bar at the end, and the plumber spends the afternoon hunting a leak that does not exist. The pipe was stretching.

Plastics pipe expands under pressure: the pipe swells, the same water fills a larger volume, and the gauge falls. The expansion is largest at first and tails off as the material creeps into its new shape. Both plastics tests share one idea — let the expansion happen first, then judge what the pressure does afterwards.

StageTest ATest B
FirstWhole system pumped to the test pressure and kept there by pumping for 30 minutesWhole system pumped to the test pressure and kept there by pumping for 30 minutes; pressure noted and pumping stopped
ThenLet down to one third of the test pressure, and left 90 minutes without pumpingLeft 150 minutes without pumping, read after 30 and after 150
Pass criterionThe pressure does not drop below one third, and no visible leakageA drop of less than 0.6 bar after the 30 minutes, or less than 0.8 bar after the 150, and no visible leakage

Dropping to one third in Test A lets the plastics relax and grip the water, so a fall below that third is a leak. Test B measures the fall from the pressure noted when pumping stops, and Schedule 2 paragraph 12(2)(b) words its limit as less than 0.6 bar after the following 30 minutes, or 0.8 bar after the following 150 minutes.

Worked example. A system under Test B drops 0.8 bar in the first 30 minutes and then holds perfectly. That is not less than 0.6 at 30 minutes, and at 150 minutes the drop is still 0.8, which is not less than 0.8, so it is a fail.

Which standard, and how to test it

BS EN 806-4, with BS 8558 alongside, sets its own procedures A, B and C at a test pressure of 1.1 times the maximum design pressure. Do not mix them up with Test A and Test B. In the UK you work to the Regulations' own test: 1.5 times the maximum operating pressure, the one-hour test on rigid pipework after the settle, and Test A or Test B on plastics.

Use a hydraulic test pump with a calibrated gauge accurate to 0.2 bar, range 0 to 16 bar, fitted at the lowest point of the system. Testing with compressed air or gas is possible but not recommended because of the risk of explosion: water is nearly incompressible, so a burst under hydraulic test releases little energy, and a gas-filled system stores a great deal.

If the pressure falls, first check that no isolating valve is passing — a valve letting by into an unfilled section drops the gauge just as a leak does. If there is a genuine drop, locate and repair the leak, then repeat the test. Have the passed test witnessed and signed, and record the pressure, duration and result.

The three shortcuts that turn a test into a lie

Twenty minutes into the hour the gauge has dropped a quarter of a bar, nobody is watching, and a quick stroke of the pump would put the needle back.

And test as the work proceeds: interim tests on each section, especially work that will be concealed, are not the same as the final test on completion. Passing an interim test does not count as the final one.

🔢 The numbers worth memorising

Test pressure
1.5 Γ— maximum operating pressure (Schedule 2 paragraph 12)
Worked example
a 3 bar system is tested at 4.5 bar
Rigid test
fill, settle 30 minutes, pump up, then one hour with no further pumping
Temperature settle
about 30 minutes after filling, before the test pressure goes on
Plastics Test A
test pressure pumped for 30 min β†’ one third of it held for 90 min, no leaks
Plastics Test B
test pressure pumped for 30 min β†’ a drop of less than 0.6 bar after 30 min, or 0.8 bar after 150
Gauge accuracy
0.2 bar, range 0–16 bar, fitted at the lowest point
Fill water
fluid category 1, direct from the main, free of particles 150 Β΅m or larger
BS EN 806-4 procedures
1.1 Γ— maximum design pressure β€” not the Regulations’ figure

⚠️ Where people go wrong

  • Filling before the drainage is connected. You will not be able to flush it.
  • Giving a plastics system the metal test. It expands under pressure, and the falling gauge is the material, not a leak.
  • Pumping straight up and starting the hour. Fill it and let the temperature settle about 30 minutes first, or the gauge moves with the water temperature.
  • Trickle-filling a distributing pipe through a half-open gate valve. Let the cistern fill and the float valve shut first, then open it fully.
  • Hunting a leak before checking whether an isolating valve is passing into an unfilled section.
  • Topping up during the hour, lowering the pressure until it holds, or recording the drop and handing over. All three are the same lie.
  • Backfilling a trench before the underground run is inspected and tested.

📝 10-Question Self-Test

Straight from the Level 3 course question bank. Click an option to see whether you got it right — the explanation appears instantly, and there is nothing to submit.

Your score: 0 / 10
Question 1 of 10
Which of these documents must be available when commissioning a cold water system and its components?
Question 2 of 10
You are about to commission a boosted cold water system in a block of flats that is already lived in. Who should be told about the work first?
Question 3 of 10
BS EN 806-4 says a finished installation is vented and then filled how?
Question 4 of 10
Copper pipework is being pressure tested to satisfy the Water Regulations. By what percentage should the water pressure at the lowest point exceed the maximum operating pressure?
Question 5 of 10
Of the following commissioning activities, which one is done first?
Question 6 of 10
A cold water installation has just been completed. Which activity begins the commissioning process?
Question 7 of 10
A cold water installation is to be filled for testing. Water of which fluid category should be used?
Question 8 of 10
When a cold water installation is filled ready for soundness testing, the filling should be done in a way that avoids
Question 9 of 10
For how long should the test pressure be held when testing a metallic pipework system?
Question 10 of 10
While soundness testing a new underground cold water system you see a large drop in pressure. What should you do?
← Previous in Cold water systemsRepairing a Cold Water System: Pumps, Backflow Devices, Galvanic Corrosion and the Seven Steps Next in Cold water systems →Flush, Disinfect, Prove: the 50 mg/l Hour and the Readings That Follow It

Going further: the lessons behind this article

This article is the public answer. Unit 331 of the Level 3 course takes the same ground to the depth the exam and the synoptic assignment ask for, in 5 lessons:

  • Visual inspection: the documents and the dry checklist
  • Direct, indirect and boosted systems: extra checks and first fill
  • Filling: avoiding air locks, stabilising and inspecting for leaks
  • Soundness testing: test pressures for metal and plastics pipework
  • Soundness testing: current standards, equipment and procedure