A customer complains that her new kitchen tap tastes metallic and leaves a green tinge in the kettle. The pipework passed its pressure test a week ago. What it never had was a proper flush.

The short answer

Schedule 2 paragraph 13 is one sentence, and the order in it is the requirement.

One sentence of law

The order of testing, flushing and disinfecting a water system
Tested, flushed, then disinfected. Schedule 2 sets that order and it does not move.
Key figures for flush, disinfect, prove
The examinable numbers from this article, in one place.

Schedule 2 paragraph 13 is one sentence: every water system shall be tested, flushed and where necessary disinfected before it is first used.

The order is the requirement. Flushing before testing would wash the evidence of leaks into the drain. Disinfecting before flushing would waste the disinfectant on debris. Testing after disinfection risks recontaminating a clean system. Each step assumes the state the previous one left the system in.

Flushing is not housekeeping

Flushing is required on every installation, whatever its size or premises. It removes swarf, jointing compound and excess flux — and flux is an acid that will corrode copper from the inside and can push the copper content over the drinking-water limit. That is the metallic taste and the green kettle.

Building debris also promotes bacterial growth, so a poorly flushed system is a contamination risk as well as a corrosion one.

The only liquid used for flushing is drinking water. And simply filling and draining is not flushing — that moves debris from one place to another. A flush has to move water fast enough to carry the debris out, through every outlet, until it runs clear.

The method

The site foreman says the system has been flushed because someone ran the ground-floor sink for ten minutes. The top-floor bathroom has never had water through it at speed.

An alternative flush uses a water/air mixture pulsed under pressure at a minimum velocity of 0.5 m/s, in sections of no more than 100 m. On a boosted system, water from the main is first introduced into the break cistern and then pumped to every point.

If a system has been flushed several times and the water is still cloudy, the trouble is upstream: report it to the water supplier. And if the system will not be used at once, flush at intervals of up to 7 days.

Cold and hot pipes are flushed separately, cold first, so clean water reaches the hot water storage. It may be necessary to flush with warm water to remove flux residues properly, because flux softens with heat.

Flushing is not only for new pipework: a cleansing flush is needed after refurbishment, after fitting new components, after a prolonged period of non-use (as little as two or three weeks), and after any work that might have introduced contamination. The school reopening in September and the holiday let opening at Easter both need one.

Which jobs need disinfecting

Three jobs land on the same morning: a new bathroom in a family house, a new cold water system for a nursing home, and a tee cut into an existing main for an outside tap. One needs disinfecting, one does not, and one gets a fitting dipped in a bucket.

Disinfection is not universal. For single dwellings, and for minor extensions or alterations in any premises, flushing is sufficient. So the family bathroom is flushed and left.

What does trigger disinfection:

How far the exception reaches. The single-family exception covers new installations and major extensions only. It does not exempt a house where contamination is suspected: a flooded cellar with the stop valve under sewage is disinfected whoever lives there. And it does nothing for a house in multiple occupation, a communal system in a block of flats, or anything commercial. The test is who the system serves, not how big it is.

The exception in the other direction is localised repairs. Inserting a junction or fitting into an existing pipe is not a new installation: the fitting is immersed in disinfectant before it goes in. Chlorinating a whole house for one fitting is not required and would inconvenience everyone in it for nothing.

The three numbers

Flush through all outlets first. Then:

StepFigure
Initial concentration of free chlorine50 mg/l — not more, because higher levels corrode copper and damage non-metallic materials
Contact timeat least one hour, starting only when the whole system, including the cistern up to overflow level, is full at 50 mg/l
Residual at the endnot less than 30 mg/l of free chlorine, measured at the furthest outlet
If the residual is below 30drain and repeat the disinfection
If it is 30 or morepass — drain immediately and flush until the residual matches the incoming supply
pH above 7.6longer contact time (pH 8 needs 2.5 hours); chlorine is not used above pH 8.5

The residual is the whole point. Chlorine is used up as it kills what it finds, so a system that starts at 50 and ends at 20 has told you it was dirtier than an hour of chlorine could deal with. It goes round again.

The sequence is service pipes, supply pipes, cisterns, then distributing pipes. On a cistern-fed system the calculated dose is added as the cistern fills, then each draw-off is opened in turn working away from the cistern until chlorinated water discharges, topping the cistern up with dosed water as it falls.

The people side

A cleaner arrives at seven in the evening, fills a bucket from the nearest tap and starts on the floors. The system is full of water at 50 mg/l of chlorine. Nobody told her, because nobody thought about who uses the building after five.

Samples for bacteriological analysis are taken after flushing, ideally two to seven days after treatment. If the results are unsatisfactory the system is flushed, re-disinfected and re-sampled.

One distinction worth holding: where contamination is in the installed system, the answer is to disinfect. Where the problem is in the incoming supply — a private borehole, say — the answer is water treatment such as UV. Chlorinating a system does nothing for contaminated water that keeps arriving, and treating the supply does nothing for a biofilm already in the pipes.

Proving it works

A system that holds pressure and has been flushed is sound and clean, but not yet proved to work. A block of flats can pass every test so far and still leave the top-floor tenant with a basin tap that dribbles.

A performance test covers pressure and flow rate at every outlet, not the kitchen sink only. Flow is measured with a weir gauge and compared with the specification or the design flow rates the system was sized on: basin 0.1 l/s, sink and shower 0.2 (minimum 0.15), bath 0.4 (minimum 0.3), garden tap 0.5 (minimum 0.4).

Static pressure is read with a gauge on an open end with no appliances running. Dynamic pressure is read while water flows and is always lower, because of friction — and it is the one the outlets actually feel.

A diagnostic worth remembering: a customer reports her loft cistern overflows, but only at night. Static pressure rises at night as demand on the main falls, so a float valve with a split washer holds at daytime pressure and lets by under the higher off-peak pressure. The commissioning lesson is to check the shut-off under the highest pressure it will see, not the pressure that happens to be there at eleven in the morning.

And take a thermometer. Cold water sitting between 20 and 45 °C is in the range where bacteria multiply, and a cold pipe run alongside a heating flow can put it there without any fault in the plumbing.

Balancing: a valve, not a bigger pump

The readings are on paper: a top-floor basin at 0.06 l/s against a design minimum of 0.1, and the ground-floor sink at 0.35 against a design of 0.2. The pump is fine and the pipe sizes are what the drawing says. The system is unbalanced, and the fix is a valve.

Water takes the easy route. Balancing means setting the floor isolating or regulating valves, or the pressure reducing valves BS 8558 recommends where pressure has to be controlled floor by floor, so that the lower floors are throttled to the design pressure and the top floor still meets its minimum.

Work from the furthest outlet back, and re-read the outlets you have already set — every adjustment moves the others. Throttling the ground floor pushes more water up the riser, which raises the top floor and may lift the middle floors above their design figure too.

In the block of flats: the ground-floor regulating valve is throttled until the sink reads 0.2 l/s, and the top basin rises to 0.11. Both readings, the pump cut-in and cut-out and the accumulator pre-charge go on the record.

Had the top floor still failed, the drawings go back to the designer — because an undersized riser cannot be balanced out. A valve can only move flow from one outlet to another; if the riser cannot carry the design total, no throttling will find it.

Setting the controls, then proving them

Setting a control puts the right number on it. Functional testing proves the system responds to that number. They are two separate checks and the exam separates them.

Set: float valve shut-off below the warning pipe with no let-by under static pressure; servicing and stop valves proved to isolate what their labels say; PRVs set with a gauge; backflow devices fitted the right way and holding; pump cut-in and cut-out, accumulator pre-charge, low-level float switch, and the pump duty against the data.

Then run it through its cycle: draw water until the pressure switch starts the pump and confirm it stops at cut-out; lower the break cistern level and confirm the low-level switch stops the pumps; on a duplicate set confirm duty and standby change over and the alarm works. Listen for cavitation and vibration, check the rotation, check for leaks at the pump.

And one rule: a pressure switch that reads far above the true system pressure on a calibrated gauge is defective and is replaced, not adjusted. Adjusting a faulty switch until its number looks right leaves a faulty switch on the system.

🔢 The numbers worth memorising

The legal order
tested, flushed, then disinfected — Schedule 2 paragraph 13
Flushing velocity
at least 2 m/s, with 20 changes of the water
Air/water pulsed flush
minimum 0.5 m/s, sections of no more than 100 m
If not used at once
flush at intervals of up to 7 days
Chlorine dose
50 mg/l free chlorine — and no more
Contact time
at least one hour, timed from when the whole system including the cistern is at 50
Residual
not less than 30 mg/l at the furthest outlet
pH above 7.6
longer contact — pH 8 needs 2.5 hours; not used above pH 8.5
Sampling
two to seven days after treatment
Cold water temperature
avoid 20 to 45 °C anywhere in the system

⚠️ Where people go wrong

  • Flushing before testing, or disinfecting before flushing. The order is the legal requirement.
  • Calling a fill-and-drain a flush. It moves debris rather than removing it.
  • Flushing only the nearest outlet. Every length of pipe, most remote first, lowest floor upwards.
  • Disinfecting a single-family house for a new bathroom. Flushing is sufficient — but the exception does not cover suspected contamination.
  • Chlorinating a whole house to fit one tee. A localised repair gets the fitting immersed.
  • Timing the contact hour from when dosing began. It starts when the whole system, cistern included, is at 50 mg/l.
  • Passing a disinfection with a residual of 20. Below 30 means drain and repeat.
  • Fitting a bigger pump for a starving top floor. That is a balancing job — unless the riser is undersized, which no valve can fix.
  • Adjusting a pressure switch that disagrees with a calibrated gauge. It is defective; replace it.

📝 10-Question Self-Test

Straight from the Level 3 course question bank. Click an option to see whether you got it right — the explanation appears instantly, and there is nothing to submit.

Your score: 0 / 10
Question 1 of 10
Sampling shows microbiological contamination inside an installed pipework system. How would an approved contractor deal with it?
Question 2 of 10
In which of these circumstances must a pipework system be both flushed and disinfected?
Question 3 of 10
Planned preventative maintenance has been carried out on a boosted cold water installation. Before it is put back into service, which parts should be flushed?
Question 4 of 10
The gauge in the image below is reading which kind of pressure?
The drawing this question refers to
Question 5 of 10
What should a performance test on a cold water system cover?
Question 6 of 10
What liquid should be used to flush through a domestic cold water system?
Question 7 of 10
After the one-hour contact period, what free residual chlorine level shows the disinfection has worked?
Question 8 of 10
Where can you find out which disinfectants are permitted for use on drinking water installations?
Question 9 of 10
What does a weir gauge test on a system against its design discharge?
Question 10 of 10
The gauge shown in the image is measuring which kind of pressure?
The drawing this question refers to
← Previous in Cold water systemsInspect Dry, Fill Slowly, Test Once: Commissioning a Cold Water System Next in Cold water systems →The Commissioning Record, the Certificates, and What Handover Actually Means

Going further: the lessons behind this article

This article is the public answer. Unit 331 of the Level 3 course takes the same ground to the depth the exam and the synoptic assignment ask for, in 5 lessons:

  • Flushing: the legal order and the BS EN 806-4 method
  • Disinfection: which jobs need it and what disinfectant is used
  • Chlorine disinfection: the figures, the people and the samples
  • Performance tests: measuring flow and pressure at every outlet
  • Balancing, mechanical controls and functional testing