Three years after handover the top-floor tenant complains of poor pressure. Was it always like that? The only honest answer is on the commissioning record.

The short answer

The commissioning record is the proof that the system does what the design said it would. It is kept for reference during maintenance, it is the baseline a fault is measured against years later, and in a non-domestic building it feeds the Legionella records that HSE ACOP L8 requires.

BS EN 806-4 requires a complete record of the pressure test, of the flushing, and of the disinfection and its results, each handed to the building owner. BS EN 806-5 makes the commissioning report part of the documentation kept for the life of the installation.

What goes on it

What goes into a commissioning record and how long it is kept
The statutory defence needs both the approved contractor and the certificate.
Key figures for the commissioning record, the certificates, and what handover actually means
The examinable numbers from this article, in one place.
SectionInformation
IdentificationDate and time, name of the commissioning engineer and company, location
The systemType of system, cold water storage volume, types and manufacturers of equipment, backflow devices fitted and where
Pressure testType of test (metal one-hour, Test A or Test B), test pressure, duration, result, witness signature
FlushingFlush time and flow rate, sections flushed, date
DisinfectionDisinfectant used, dose in mg/l, contact time, residual at the end of contact, residual after flushing, neutralising agent if any, sampling results, date, and who carried it out
PerformanceStatic and working pressures, flow rates at every outlet, pump suction and discharge pressures, pump cut-in and cut-out, accumulator pre-charge, PRV settings
DefectsAnything found, what was done about it, and the retest

What does not

Payment terms belong to the contract and the invoice. Delivery dates of plant, the supplier of the copper tube, the brand of flux or solder, the weather, the vehicle registration and the time you arrived on site are none of them commissioning results.

The names and qualifications of the installers, and the method statements and permits used during installation, belong in the health and safety file and the water management logbook — though the record does name the person or company who carried out the disinfection.

Under ACOP L8 paragraph 72, records of monitoring, inspection, tests and checks are kept for at least five years.

When commissioning finds a fault

Commissioning is the first time the system runs, so it is when problems appear — and finding them is what commissioning is for. The rule is: correct items failing any test immediately and re-test them before further work proceeds. A defect is never carried forward or left for the maintenance contractor to find.

What you do next depends on the kind of defect, and the split between "yours to fix" and "somebody else's decision" is examined:

Every defect and its remedy goes on the record, with the retest that proved it fixed, and nothing is handed over until the retest passes.

Notification, seen from the other end

Two jobs, same week. A new bathroom in a private house, and a new-build house waiting for its service connection. The customer on the first asks whether the water company has to be told. The site agent on the second assumes it does not. Both have it the wrong way round.

Work in a private house that is only an extension or alteration is not notifiable, because item 2 of the Regulation 5 Table says "premises other than a house". So the new bathroom needs no notice. But before a new house is connected the undertaker must have been notified, because erecting a building is item 1, and consent is needed before the fittings are installed and connected.

Both traps cut against instinct: a big job in a house can be done without a word to the water company; a modest new build cannot. The test is which line of the Table the work sits on, not its size.

And the last step, easily forgotten: when all tests have passed, the water supplier is told the system is ready for permanent connection.

The certificates

Whether you can write a certificate of compliance depends on one thing: whether you are an approved contractor — approved by the undertaker for the area, or certified by an organisation specified in writing by the regulator.

Under Regulation 6, an approved contractor must on completion give a signed certificate of compliance to the person who commissioned the work, and where the work was notifiable, send a copy to the undertaker.

The reason it matters is Regulation 7(2): the owner or occupier has a statutory defence only where the work was done by an approved contractor and the contractor certified it. Approval without a certificate fails. A certificate from somebody not approved fails too.

Separately, Building Control wants its own paperwork — a completion notice on a building notice or full plans route, or a competent person's certificate within 30 days.

What handover actually means

Handover is not dropping an envelope through the door. The customer gets three things: the documents, a demonstration, and the knowledge to act in an emergency.

The handover file holds the undertaker's acceptance, the compliance certificates, the commissioning records, the as-fitted drawings and every manufacturer's instruction book. Where the building has a water management regime, it also holds the schematic diagrams and the log the next engineer will write in.

The demonstration is the part people skip and the part customers remember. Walk them round and explain the working principles of the controls — what the booster set does and what its alarm means, what the softener needs, how the WC servicing valves work. Show them the isolation points, and make them turn the stop valve themselves once, so they know it moves and where it is at two in the morning.

Then the record goes in the logbook, and the system stops being your job and starts being theirs — with a written baseline so that in three years, when the top-floor tenant complains, there is an honest answer to "was it always like that".

🔢 The numbers worth memorising

Record retention
at least five years (ACOP L8 paragraph 72)
Pressure test entry
type, pressure, duration, result, witness signature
Disinfection entry
disinfectant, dose, contact time, residual, sample results, who did it
Performance entry
static and working pressures, flow rate at every outlet
Statutory defence
needs an approved contractor AND a certificate (Regulation 7(2))
Competent person certificate
to the occupier within 30 days
Extension in a house
not notifiable — item 2 says "premises other than a house"
Erecting a building
is notifiable — item 1, consent before fittings are connected

⚠️ Where people go wrong

  • Putting payment terms, delivery dates or the flux brand on a commissioning record. It holds technical results.
  • Leaving a defect for the maintenance contractor. It is corrected and re-tested before further work proceeds.
  • Accepting a component that does not match the specification. That goes to your manager, not into the system.
  • Repairing a defective new component yourself. It goes back to the manufacturer and supplier — a repair can void the warranty.
  • Assuming a big job in a house needs notifying and a small new build does not. It is the Table line, not the size.
  • Writing a certificate of compliance without being an approved contractor. It gives the customer no defence at all.
  • Handing over an envelope. The demonstration and the isolation points are part of handover, not an extra.

📝 10-Question Self-Test

Straight from the Level 3 course question bank. Click an option to see whether you got it right — the explanation appears instantly, and there is nothing to submit.

Your score: 0 / 10
Question 1 of 10
Which set of items belongs on the commissioning record for a cold water installation?
Question 2 of 10
The water system in a private house is being extended and altered. What notification procedure do the Water Regulations require for this work?
Question 3 of 10
At handover of a cold water system, which of these should be explained to the end user?
Question 4 of 10
Which of the following gives a customer the best assurance that the work has been finished to the required standards?
Question 5 of 10
A boosted cold water system in a block of flats is being commissioned. Which of these belongs on the commissioning record?
Question 6 of 10
A large cold water supply system in a residential care home is being commissioned. Which of these should go on the commissioning record?
Question 7 of 10
For which of these items should the customer be given operating instructions?
Question 8 of 10
Which of the following should the plumber show the customer how to do?
Question 9 of 10
The sample results come back unsatisfactory after testing. What should be done to put this right?
Question 10 of 10
While commissioning a cold water installation, which of these should be recorded in detail?
← Previous in Cold water systemsFlush, Disinfect, Prove: the 50 mg/l Hour and the Readings That Follow It Browse all articles →Every PlumbMate article

Going further: the lessons behind this article

This article is the public answer. Unit 331 of the Level 3 course takes the same ground to the depth the exam and the synoptic assignment ask for, in 4 lessons:

  • The commissioning record and the defects that go on it
  • Regulation 5 notification and the certificates of compliance
  • Handover: the file and the demonstration
  • After handover: signing off and the routine user checks